Difference between revisions of "Running Daily Phase 2 Summary"
Jump to navigation
Jump to search
Line 1: | Line 1: | ||
=== Mar 10, 2023 === | === Mar 10, 2023 === | ||
− | |||
* Max | * Max | ||
:: ...running final beam test, plans to wrap up today, latest Sunday | :: ...running final beam test, plans to wrap up today, latest Sunday |
Latest revision as of 09:35, 10 March 2023
Mar 10, 2023
- Max
- ...running final beam test, plans to wrap up today, latest Sunday
- ...coordinating w/ DC Power and I&C to de-energize and disconnect cables to magnets and bpm's
- Marcy
- ...polishing CEBAF install work plan gantt chart, will circulate and review on Monday
- ...coordinating w/ Vince for modification of "blue" HV chamber base plate next week
- Joe
- ...found Gun2 has Bulk #32 puck for HV conditioning (i.e. don't need to bring one from UITF) - https://logbooks.jlab.org/entry/3876517
- ...things to do on Monday ... isolate laser, vacuum valves, disconnect electrical things, stow pucks, HV cable disconnect, move toward clean room
- Steve
- ...has plan to work with Scott and to document racks/controls during SAD
- ...let's review laser plan with Shukui (replace Hall A mode-lock with temp regulating seed, continue developing/testing new board for later upgrade)