Difference between revisions of "Running Daily Phase 2 Minutes"
Jump to navigation
Jump to search
Line 3: | Line 3: | ||
:: ...found Gun2 has Bulk #32 puck for HV conditioning (i.e. don't need to bring one from UITF) - https://logbooks.jlab.org/entry/3876517 | :: ...found Gun2 has Bulk #32 puck for HV conditioning (i.e. don't need to bring one from UITF) - https://logbooks.jlab.org/entry/3876517 | ||
:: ...things to do on Monday ... isolate laser, vacuum valves, disconnect electrical things, stow pucks, HV cable disconnect, move toward clean room | :: ...things to do on Monday ... isolate laser, vacuum valves, disconnect electrical things, stow pucks, HV cable disconnect, move toward clean room | ||
− | :: ... | + | :: ...EH&S approved their part (but needs HV OSP in place if we go that route) => * ATLIS => https://tasklists.jlab.org/atlis/tasks/108541 |
* Max | * Max | ||
:: ...running final beam test, plans to wrap up today, latest Sunday | :: ...running final beam test, plans to wrap up today, latest Sunday |
Revision as of 10:59, 10 March 2023
Mar 10, 2023
- Joe
- ...found Gun2 has Bulk #32 puck for HV conditioning (i.e. don't need to bring one from UITF) - https://logbooks.jlab.org/entry/3876517
- ...things to do on Monday ... isolate laser, vacuum valves, disconnect electrical things, stow pucks, HV cable disconnect, move toward clean room
- ...EH&S approved their part (but needs HV OSP in place if we go that route) => * ATLIS => https://tasklists.jlab.org/atlis/tasks/108541
- Max
- ...running final beam test, plans to wrap up today, latest Sunday
- ...coordinating w/ DC Power and I&C to de-energize and disconnect cables to magnets and bpm's
- Marcy
- ...polishing CEBAF install work plan gantt chart, will circulate and review on Monday
- ...coordinating w/ Vince for modification of "blue" HV chamber base plate next week
- Steve
- ...has plan to work with Scott and to document racks/controls during SAD
- ...let's review laser plan with Shukui (replace Hall A mode-lock with temp regulating seed, continue developing/testing new board for later upgrade)