Difference between revisions of "MOLLER PQB Meeting July 24, 2024"
Jump to navigation
Jump to search
Line 18: | Line 18: | ||
# New gun HV chamber installed, laser retro-reflection next week | # New gun HV chamber installed, laser retro-reflection next week | ||
− | # All MFX solenoids were fixed: [[MFX_fix. | + | # All MFX solenoids were fixed: [[media:MFX_fix.jpg]] |
# New RTP HV Driver EH&S review this week | # New RTP HV Driver EH&S review this week | ||
* '''MOLLER new rack in ISB - IN03B25''': [[media:IMG_1695.jpeg]] | * '''MOLLER new rack in ISB - IN03B25''': [[media:IMG_1695.jpeg]] |
Revision as of 12:10, 24 July 2024
In person in MCC Conference Room and with Zoom.
https://wiki.jlab.org/ciswiki/index.php/Parity_Quality_Beam
--
Agenda:
- Beam Study Results:
- FFB/FF in Hall A:
- Check S/H wiring of the Hall A BPMs in BSY
- Check FFB ON versus OFF in QWeak data
- 2010 QWeak Data: [1]
- Injector Upgrade Progress:
- New gun HV chamber installed, laser retro-reflection next week
- All MFX solenoids were fixed: media:MFX_fix.jpg
- New RTP HV Driver EH&S review this week
- MOLLER new rack in ISB - IN03B25: media:IMG_1695.jpeg