* '''Injector Upgrade Progress:''' | * '''Injector Upgrade Progress:''' | ||
− | # New gun HV chamber installed, laser retro-reflection | + | # New gun HV chamber installed, laser retro-reflection and gun alignment start on Monday |
# All MFX solenoids were fixed: [[media:MFX_fix.jpg]] | # All MFX solenoids were fixed: [[media:MFX_fix.jpg]] | ||
# New RTP HV Driver passed EH&S review. Non-NRTL inspection is scheduled for next this week | # New RTP HV Driver passed EH&S review. Non-NRTL inspection is scheduled for next this week |
Revision as of 13:43, 24 July 2024
In person in MCC Conference Room and with Zoom.
https://wiki.jlab.org/ciswiki/index.php/Parity_Quality_Beam
--
Agenda:
- Beam Study Results:
- FFB/FF in Hall A:
- Check S/H wiring of the Hall A BPMs in BSY
- Check FFB ON versus OFF in QWeak data
- 2010 QWeak Data: [1]
- Injector Upgrade Progress:
- New gun HV chamber installed, laser retro-reflection and gun alignment start on Monday
- All MFX solenoids were fixed: media:MFX_fix.jpg
- New RTP HV Driver passed EH&S review. Non-NRTL inspection is scheduled for next this week
- MOLLER new rack in ISB - IN03B25: media:IMG_1695.jpeg