GTS meeting 10 16 17

From Ciswikidb
Revision as of 10:46, 16 October 2017 by Suleiman (talk | contribs)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
  • Shutdown Plan:
  1. Install new YAG screen at viewer 3
  2. Fix existing harp and install 20 µm tungsten wire
  3. Add a new CEBAF-style harp with 10 µm tungsten wire (i.e, GTS will have two harps)
  4. Fix leaky vent valve
  5. Activate new photocathode (new puck) with full active area


  • Map RadiaBeam steerer and measure the electrical characteristics (e.g., time constant)


  • Next Shutdown – January 2018:
  1. Install TE011 cavity


  • High current runs: [1]