We need this information to present to Andrei as our plan for the remainder of FY21 and ask for his guidance going forward.
FY21 Schedule Discussion:
- Wastewater Irradiation Experiment Setup/Support (McCaughan)
- Booster Assessment and Commissioning (Kazimi)
- Booster Removal & Relocation for Injector Phase 2 Upgrade (Poelker) media:poelker_mccaughan UITF plans for rest of 2021
- 200 kV Gun + Reliability (Grames)
- Warm RF Photocathode Studies (Grames)
Please estimate the duration and resource (personnel, utility/cryogen, space) requirements for your tasks and experiments.