  • First installation
    • remove ~4' pipe in straight passthrough
    • add reducer + ceramic break + bubble radiator
    • add MIT bates magnet + Mott detector on the support table
    • realistic time frame for DAQ
  • Second installation
    • Replace MIT magnet with Lakshmi's magnet
    • Replace Mott detector with Eric's detector