GTS meeting 3 07 17

From Ciswikidb
Revision as of 08:16, 7 March 2017 by Suleiman (talk | contribs)
Jump to navigation Jump to search
  • Measured QE ~ 3.5% with -100 V Gun bias. Was about 0.4% with -1 kV bias.
  • Gun vacuum improved when opeening the gate valve to beamline – beamline vacuum went higher.
  • Beam to F-Cup
  • Plan to complete the second part of beamline in two weeks: plan for one-week down in about 2 weeks to install the second DP can, solenoid, ion precipitator and the BNNT diagnostic station.