GTS meeting 9 11 17
Jump to navigation
Jump to search
- High current runs
- Shutdown Plan:
- Install new YAG screen at viewer 3
- Fix existing harp and install 20 µm tungsten wire
- Add a new CEBAF-style harp with 10 µm tungsten wire (i.e, GTS will have two harps)
- Replace leaky vent valve
- Replace bad ion pump
- Next Shutdown – December 2017:
- Install TE011 cavity