GTS meeting 2 04 19
Jump to navigation
Jump to search
List of beamline hardware modifications
- Replace YAG screen on Viewer 1 - Done
- Replace Slit on Viewer 2 with holes assembly - Done
- Replace two ion collectors with new ones - Done
- Replace Harp fork (Tony)
- Remove modified DP can - Done
- Remove Faraday Cup - Done
- Remove bellow upstream of dump - Done
- Remove LDR Harp arm and replace with ion-pump
- Rotate Viewer 3 to vertical - Done
- Install TE011 Cavity
- Install Deflecting Cavity - Done
- Install new 5th solenoid
- Move DP can 1 to end of beamline - Done
- All bellows at least 2.5 inch diameter - Done
- Both gate valves are 2.5 inch-bore and will remain on beamline - Done
- S&A on Friday February 8, 2019
List of hardware support
- Install Deflecting Cavity power supply, MO and other parts
- Install TE011 Cavity readout cable and electronics
List of software and controls changes
- Re-program SCAM to allow for 1 Hz and 50 ns macro-pulses
- Add 5th solenoid to magnet screen
Remove gain-switched laser (seed and pre-amp) from GTS to LERF
Install Brock's Magnetometer Cavity
Modification to HV and Preparation chambers
- Upgrade anode HV bias feed-through to 5 kV
- Remove anode and clean melted spot
- Fix Transverse Manipulator
- Fix Sb boat
- Clean Sb pellets off chamber