GTS meeting 2 11 19
Jump to navigation
Jump to search
List of completed beamline hardware modifications
- Replace YAG screen on Viewer 1
- Replace Slit on Viewer 2 with holes assembly
- Replace two ion collectors with new ones
- Replace Harp fork (Tony)
- Remove modified DP can
- Remove Faraday Cup
- Remove bellow upstream of dump
- Remove LDR Harp arm and replace with ion-pump
- Rotate Viewer 3 to vertical
- Install TE011 Cavity
- Install Deflecting Cavity
- Install new 5th solenoid
- Move DP can 1 to end of beamline
- All bellows at least 2.5 inch diameter
- Both gate valves are 2.5 inch-bore and will remain on beamline
- S&A on Thursday February 7, 2019
List of hardware support
- Install Deflecting Cavity power supply, MO and other parts
- Install TE011 Cavity readout cable and electronics
List of software and controls changes
- Re-program SCAM to allow for 1 Hz and 50 ns macro-pulses
- Add 5th solenoid to magnet screen