CIS Phase 1 work plans

From Ciswikidb
Jump to navigation Jump to search

Week 1 (Sep 21 - Sep 27) High Voltage Testing w/ PSS lock-ups

Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects

Fri 9/25 - Mon 9/28
  • CIS Gun Jobs
Wien electrode testing โ€“ 9am!!!
Gun HVPS lockout - DONE
Gun HV cable disconnect โ€“ DONE
Remove PIG โ€“ Coordinate w/ Neil for convenient time
Shukui - Laser outrigger table as-founds, remove components
Scott - Remove yellow box
Scott - Disconnect Decarad
Monday 9/28 Tasks (updated 0915 9/28)
  • Power down Wein system (Scott/Joe)
  • Power down and remove DecaRad system (Scott)
  • Return gun valve config to "normal" (Marcy)
  • Dispose of grey mineral oil tank in coordination w/ESH&Q (Carlos/Bubba)
  • PSS Kickers and associated chassis removal (SSG)
  • Laser table disassembly (Shukui/Scott)
Tuesday 9/29 Tasks (updated 0930 9/29)
  • (Done) Disconnect BPMs 2I01->0I02A (Pete) beginning 5a
  • (Done) Disconnect aperture and cup signal cables (Pete) 5a
  • Disconnect rad probes (Melvin) 8a
  • Tunnel magnet disconnects (Diggs, Delk) 10a
  • (Done) Removal of old chopper amps from rack (Farrish)
  • Harp upgrade to PC104 (Dela Cruz)
  • ODH Head Replacements (SSG)
  • Document existing Wein cabling and power off PS (Scott)
Wednesday 9/30 Tasks (updated 0900 9/30)
  • RF Prebuncher disconnects (Farrish) 6a
  • Vacuum Component Labeling (Greenfield, Gonzales) 430a
  • Magnet disconnects -- wire wrap-ups, junction box investigation (Coleman, Diggs, Delk) 10a
  • Tiny magnet removals (Scott, Grames) 9a
  • PSS Kicker Magnet removal (SSG) 9a
  • Sample hold cables install, InjSB (Francis)
  • Remaining PSS Interface chassis removal (SSG)
  • Harp upgrade to PC104 (Dela Cruz)
  • Moser transfers CCOC phone @1430, to reach moving forward x5089
Thursday 10/1 Tasks (updated 0830 10/1)
  • Picoammeter Removal, InjSB (Francis) 5a
  • Sample hold cables install, IN02B24 (Francis)
  • BPM Work in IN02B2* (Francis)
  • Chopper amplifier upgrade (Farrish)
  • Harp upgrade to PC104 (Dela Cruz)
  • Viewer+harp hardware disconnects (Norris, Dela Cruz) 6a
  • Disconnecting water and air lines from apertures and cups (Adderley) 8a
  • Mech Install Pre-Job Walk-Thru (Grames, Wilson) 9a
Friday 10/2 Tasks (updated 0900 10/2)
  • Viewer disconnects (Norris) 6a
  • BPM Work in IN02B2* (Francis)
  • Chopper amplifier upgrade (Farrish)
  • Harp upgrade to PC104 (Dela Cruz)
  • PSS Kicker Cables tie-up (SSG)
  • Survey and Alignment control measure around gun (S&A)
  • Load suitcase with "bad" pucks (CIS)
  • Pump-down vacuum in front of tee for next week (CIS)
Tunnel Work
Time Mon 9/28 Tue 9/29 Wed 9/30 Thu 10/1 F 10/2
4a - 8a I&C; 5a: Francis: BPMs, Cups, Apertures I&C; 430a: Greenfield + Gonzales: vacuum labelling; 6a: Farrish: Prebuncher I&C; 6a: Norris: Viewer; 6a: Dela Cruz, Harps I&C: Norris: Viewer disconnects
8a - 10a CIS + SSG RadCon: rad probes SSG: Kicker magnet removal; CIS: Tiny magnet removals CIS; Adderley: Aperture+Cups Air/Water; Grames: Mech Install Walk-Thru S&A: Gun
10a - 12p CIS + SSG DC Power DC Power: Wire wrap-ups, junction box investigation S&A: Gun; SSG: Kicker cable tie-up
12p - 2p CIS + SSG DC Power DC Power: Wire wrap-ups, junction box investigation DC Power S&A: Gun
2p - 4p CIS + SSG DC Power 3p: Moser: Safety Warden checks S&A: Gun
4p - ??
Other Work Occurring When Convenient
  • Remove suitcase, Tunnel (CIS)
  • Harp upgrade, InjSB (I&C)
  • ODH Head Replacement, InjSB and Tunnel (SSG)
  • PSS Chassis Removals, InjSB (SSG)

Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network

Monday Oct 5
  • vacuum tests, disconnects, and pre-removal blank offs (CIS)
  • QCM->downstream Survey and Alignment
  • S&H cable work for iocinse4, InjSB (Francis)
Tuesday Oct 6
  • Survey and Alignment finishing up around 0L04 (S&A)
  • U-tube operations at 0L03 (Cryo)
  • S&H cable work for iocinse4, InjSB (Francis)
  • Stage/prepare for craning our girders (Mech Install)
  • Chopper SSA upgrade -- LCW line install, InjSB (Mech Install / RF)
Wednesday Oct 7
  • S&H cable work for iocinse4, InjSB (Francis)
  • Chopper SSA upgrade, InjSB (Farrish)
  • Wein PS Work, InjSB (Windham)
  • VIP UHV PS Work, InjSB (Windham)
  • Harp PC104 upgrade, InjSB (Dela Cruz)
Thursday Oct 8
  • BPM work, InjSB (Francis)
  • Chopper SSA upgrade, InjSB (Farrish)
  • Harp PC104 upgrade, InjSB (Dela Cruz)
Wednesday Oct 7 and Thursday Oct 8 -- Mechanical Install
  • Remove to test lab --
    • Laser outrigger table
    • 1st Wein girder and pedestals
    • 2nd Wein girder, apertures, and pedestals
    • Photocathode puck suitcase on cart
  • Remove to Brett Lewis grey oil tank
  • Penetration stone drops

Current list of Injector penetrations to be dropped: 57, 86, 108, possibly this one

Penetration drop distance e3854100:

  • 34ft from floor of InjSB to floor of Inj tunnel
  • 25ft from floor of InjSB to elevated Inj tunnel cable tray
Friday Oct 9
  • BPM Work, InjSB (Francis)
  • Chopper SSA upgrade, InjSB (Farrish)
  • Harp PC104 upgrade, InjSB (Dela Cruz)
  • Penetration stone drop -- 57, 86, 108, Tunnel (Mech Install)
    • Penetration above laser hut already opened

Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild

  • Laser/Y-Chamber viewer for Y-chamber girder (Marcy)
  • Fiducializing Y-chamber girder (S&A)
  • Laser window under vacuum evaluations (Phil/Shukui/Caryn)
  • Documenting early InjSB racks (Scott)
  • Cable pulls through penetrations (EES)
  • Fire pipe demolition? (Facilities Contractor)
  • Wein upgrade (Carlos) --
    • Finish new Wien electrodes drawing and sign-offs
    • Vacuum chambers to machine shop for mods
    • Begin creating new screens
  • Injector Tunnel Photos from W 10/14


Monday Oct 12

Tunnel --

  • Hooking up VIPs to new 18V PS for load testing (Marcy/Scott)
  • Cable pulls through penetrations (EES)

InjSB --

  • BPM Cable Pulls through Penetration 86 (Francis)
  • Chopper SSA upgrade (Farrish)
  • Harp to PC104 upgrade (Dela Cruz)
  • Early rack documentation and space optimization (Scott)
  • PSS Upgrade work (IN02BNI, B29, B30) (SSG)


Tuesday Oct 13

Tunnel --

  • Cable pulls through penetrations (EES)
  • Resistor box evaluation (Coleman)

InjSB --

  • BPM Work, IN02B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)


Wednesday Oct 14

Tunnel --

  • Cable pulls through penetrations (EES)
  • Safety warden walk-through (Moser)

InjSB --

  • BPM Work, IN02B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • Determining rack location for Wien magnet PSs, IN02-middle (Coleman, Grames, Moser)
  • Safety warden walk-through (Moser)
  • Conduit in penetration 135 (Electricians)


Thursday Oct 15

Tunnel --

  • S&A Level surveys

InjSB --

  • BPM Work, IN0{2,3}B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • 20A PS Install, Rack re-org, IN02B22 (DC Power)
Friday Oct 16

Tunnel --

  • Cable pulls through penetrations (EES)
  • Mott cable removals (Scott/Riad, EES)

InjSB --

  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • 20A PS Install, Rack re-org, IN02B22 (DC Power)
  • IN02B26 Power Lock-Out, ~915a (DC Power)

Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation

Non-Tunnel Work
  • Build new Y-chamber viewer => Y-built w/test screen, Laser being built.
  • Use test screen + laser + S&A to verify position of first viewer => This week
  • Install + align + vacuum seal (2) viewers => target this week
  • Caryn will confirm but identified best โ€˜mushroomโ€™ window, attach => done
  • ME provide ALL points to S&A for installation (gun table, 2I stand, Y-chamber, 2 peds for Wien, 2 peds A1/A2) => ???
  • Carlos' Wien-mania!
Tunnel Work
  • Complete remove old keV Mott cables => done
  • Complete remove old gun HV cables => done
  • Jim pulls Wien PS cables? => done
  • Does Wien HV cable pull start? => starting this week
  • Scott will finish tie back of cables on tunnel floor to cable tray => done
  • Refill 86? => no, not yet
Standing Injector Service Building Work
  • BPM Work, IN0{2,3}B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • 20A PS Install, Rack re-org, IN02B22 (DC Power)
Monday Oct 19

Tunnel --

  • Cryo u-tube pulls for 0L0{2,3,4}
Tuesday Oct 20

Tunnel --

  • Cable pulls and removals

InjSB --

  • BPM Work, IN0{2,3}B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • 20A PS Install, IN02B22, 2p - 4p (DC Power)
Wednesday Oct 21

Tunnel --

  • S&A Verify line with new control

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (SSG - single person)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
  • M56 Hardware Removal from IN02B22, (I&C)


Thursday Oct 22

InjSB --

  • Wien Magnet PS Install, IN02B22, afternoon (DC Power)
  • Early rack documentation and space optimization, IN01B{00-05}, 9a - 4p (Windham)
  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (SSG - single person)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)


Friday Oct 23

Tunnel --

  • Vacuum work clean room craned in 6a - 8a (Mech Install)
  • Clean room setup and prepping (Marcy)
  • Gun interlock checks in preparation of removal of old HV Interlock Chassis in IN01B02 (Windham, Grames)
  • Laser room work (Shukui)

InjSB --

  • Early rack documentation and space optimization, IN01B{00-05}, 9a - 4p (Windham)
  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
  • 20A PS Install, IN02B22 (DC Power)


Inj Service Building Work

InjSB Racks.png

Time Wed 10/21 Thu 10/22 Fri 10/23
5a - 9a Dela Cruz, Norris, Francis Dela Cruz, Norris, Francis Dela Cruz, Norris, Francis
9a - 12p Francis, SSG, Windham Francis, SSG Francis, SSG, Windham
12p - 4p DC Power, SSG, Windham, Francis DC Power, SSG, Windham, Francis DC Power, SSG, Windham, Francis

Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move Gun2 new location

Tunnel work
  • Remove NEG filter from HV chamber โœ…
  • Setup mobile cleanroom over HV chamber โœ…
  • Vent Gun3 chamber to test Gun3 valve โœ…
  • Vent Gun2 chamber to test Gun2 valve โœ…
  • Remove 2I NEG beam line, remove NEG pedestal (temporarily) โœ…
  • Replace 10โ€ flange + SHV connector + blank off + pump down โœ…
  • Prep Gun3 & Y-chamber for Install to remove โœ…
  • Wrap up UHV ion pump power supply power tests โœ…
  • INSTALL lift and move gun table off feet, & move Gun3 & Y-chamber back to TL-1137 โœ…
  • S&A may start setting/checking points (gun feet, 2I ped, Y ped, Wien ped, A1/A2 ped) โœ…
Non-Tunnel Work
  • Finish Y-chamber : add viewers, add laser vacuum window, add NEG towers, add gun valve on-going
  • Wien-mania! (high level schedule)
-Wien magnetic field mapping next couple weeks
-Bubba assembles the fixtures โœ…


Injector Tunnel and Service Building Work

Location
Time
Mon 10/26 Tue 10/27 Wed 10/28 Thu 10/29 Fri 10/30
InjSB
5a - 9a
Norris, Dela Cruz, Francis Norris, Dela Cruz, Francis Norris, Dela Cruz, Francis Norris, Dela Cruz, Francis Norris, Dela Cruz, Francis
Tunnel
5a - 9a
Gun Vacuum Work Gun Vacuum Work Gun2 Table Move
Y-Chamber+Gun3 Removal
InjSB
9a - 12p
Francis, SSG Francis, Windham, SSG Francis, Windham, SSG Dela Cruz, Norris, Francis, SSG Francis, SSG
Tunnel
9a - 12p
Gun Vacuum Work Gun Vacuum Work 9a CIS+MechInstall Walk-Thru Wien Cable Pulls Cryo 0L02 L-tube pull
Fire pipe walk thru
S&A Point Layouts
InjSB
12p - 4p
SSG Windham, SSG Windham, SSG
Trim Rack Checks
SSG SSG
Tunnel
12p - 4p
Gun Vacuum Work Gun Vacuum Work
3p:Videographer Tour
S&A Point Layouts

InjSB Week6.png


Mon Oct 26

Tunnel --

  • Gun vacuum work, 9a - 4p (CIS)

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
  • 20A Wien Magnet PS Install, IN02B22 (Coleman)
  • LLRF air temperature control system removal from IN01B13? (Plawski?)
Tues Oct 27

Tunnel --

  • Gun vacuum work, 9a - 3p (CIS)
  • Videographer Tour, 3p+ (K. Carter + two videographers)

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
  • CIS Rack Work, IN01B{00-05} 9a - 4p (Windham)
  • 20A Wien Magnet PS Install, IN02B22 (Coleman)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • LLRF air temperature control system removal from IN01B13? (Plawski?)
Wed Oct 28

Tunnel --

  • CIS + MechInstall Walk-Through of Gun Table Move, Removal of Gun3 stub and Y-chamber, 9a

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
  • CIS Rack Work, IN01B{00-05} 9a - 4p (Windham)
  • Trim Card Checks, IN02B{10+11+26} + IN04B10, 12p-1p (Richardson)

Other Possible Work....

  • 20A Wien Magnet PS Install, IN02B22 (Coleman)
  • Chopper SSA upgrade, back of IN01B{03-11}, (Farrish)


Thur Oct 29

Tunnel --

  • Gun2 move, 5a - 8a (Mech Install)
  • Removal of Gun3 and Y-chamber to Test Lab, 5a - 8a (Mech Install)
  • Wien HV and control cable pulls, 9a - 1p (Dela Cruz)

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Wien controls work, IN01B03, 6a - 1p (Dela Cruz)
  • Viewer work, IN03B07, 6a - 1p (Norris)
  • BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)

Other possible work....

  • 20A Wien Magnet PS Install, IN02B22 (Coleman)
  • Chopper SSA upgrade, back of IN01B{03-11}, (Farrish)
All Hallows' Eve Eve ๐Ÿ‘ป (Fri 10/30)

Tunnel --

  • Cryo L-tube Removal from 0L02, 8a - 12p (Cryo)
  • Fire pipe demo job walk-through, 12p (Grames, Suhring, Renzo)
  • Point Layouts, after cryo (S&A)

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Wien controls work, IN01B03, 6a - 1p (Dela Cruz)
  • Viewer work, IN03B07, 6a - 1p (Norris)
  • BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)

Other possible work....

  • 20A Wien Magnet PS Install, IN02B22 (Coleman)
  • Chopper SSA upgrade, back of IN01B{03-11}, (Farrish)

Week 7 (Nov 2 - Nov 6)

Fire pipe removal, viewer design, modify existing pedestals, Wien filter mapping

Tunnel work
Mon/Tue
  1. INSTALL crane support (move Y-girder, Gun3 chamber, anything else back to TL1137)
  2. CIS take opportunity to a) cover your stuff before fire pipe demo, b) clean up cabinets, toolbox
  3. EES-IC Cable Pulls, Termination, and Routing
Wed/Thu and maybe Fri
  1. Fire pipe demolition
Non-Tunnel Work
  • Complete Y-chamber: add viewers, add laser vacuum window, add NEG towers, add gun valve
  • Wien-mania! (high level schedule) => H/V-wien magnetic field mapping
InjSB Work
  • Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos) --
    • Comm chassis to digiport server
  • PSS Upgrade, IN02B{NI, 29, 30} (Beizer)
  • Viewer work, IN03B0{6+7} (Norris)
  • BPM Work, IN03B{05-08, 23} (Francis)
  • CIS Rack Work, IN01B{00-05} (Windham)

Other possible work...

  • 20A Wien Magnet PS Install (Coleman)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)

Injector Tunnel and Service Building

Location
Time
Mon 11/2 Tue 11/3
Election Day ๐Ÿ‡บ๐Ÿ‡ธ
Wed 11/4 Thu 11/5 Fri 11/6
InjSB
5a - 9a
BPM, Viewer, Wien Work BPM, Viewer, Wien Work BPM, Viewer, Wien Work BPM, Viewer, Wien Work BPM, Viewer, Wien Work
Tunnel
5a - 9a
Wien + viewer cable pulls
INSTALL Crane Outs
Wien + viewer cable pulls Fire pipe demo Fire pipe demo F(riday)
InjSB
9a - 12p
PSS Upgrade
BPM, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
BPM, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
BPM, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
BPM, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
BPM, Viewer, Wien Work
CIS Rack Work
Tunnel
9a - 12p
Wien + viewer cable pulls Wien + viewer cable pulls Fire pipe demo Fire pipe demo F(loat)
InjSB
12p - 4p
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
Tunnel
12p - 4p
M T Fire pipe demo Fire pipe demo F

InjSB Week7.png

Week 8 (Nov 9 - Nov 13) Beamline anchors/pedestals, Wien mapping/HV system, A1/A2 cubes, prebuncher

Tunnel work
  1. Tue - S&A is queued up to set new(er) gun foot pad points
  2. Tue/Wed - Shaun predicts 4 pedestals arrive, Jenord inspects them; other peds exist in tunnel - thank you Phil/Shaun!
  3. Wed/Thu/Fri - Install drills and drops anchors, prepare grout form?, maybe we return gun table (Tom, best guess for the fire pipe install?)
ME work
  • S&A drop revised points for table base pads. ECD 11/10. done
  • 2I solenoid โ€“ done
SG print full size drill template for Neil.
Check fit of template.
  • Neil โ€“ Drill holes into top of solenoid stand (existing item and is currently in place) using drill template provided by Shaun. done
  • Neil drill anchor holes in floor done
HVC table base pads. done
Wien Girder Pedestals. done
Aperture Girder Pedestals. done
Details have been provided to Neil. done
  • Y chamber girder
Design new v-block mounting for Y & ion pump due to angle change of Y.
Fabricate or modifications.
Non-Tunnel Work
  1. Wien-mania! (high level schedule) - Wien magnet mapping, HVPS system controls (ADC/DAC), Switchbox build
  2. Complete Y-chamber build : laser window + (2) viewers + NEG Tower + Valve (gun3!?)
  3. A1/A2 cube assemblies - (2) for vacuum testing, (1) for magnet fit-up/testing
  4. Prebuncher vacuum repair, leak check
  • Did the leak check braze joint happen?
  • Did a final probe port length get decided?
  • Can we resolve these question, repair the probe port, clean, ready for testing by Friday?
  1. Submit PR for PSS kicker
ISB Work
  1. Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos) --
    • Wire HV PS
    • Install Comm chassis
  2. PSS Upgrade, IN02B{NI, 29, 30} (Beizer)
  3. Viewer upgrades, IN03B07 (Norris)
  4. Harp upgrades, IN03B07 (Dela Cruz)
  5. BPM Work, IN03B{05-08, 23} (Francis) Phase I: โœ…; jump-start on Phase II โœ…
  6. CIS Rack Work, IN01B{00-05} (Windham)
  7. Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  8. First Aid Cabinet re-stocks, back wall behind IN02B22ish + bottom of access stairs, (Occ Med + vendor), date TBD

Injector Tunnel and Service Building

Location
Time
Mon 11/9 Tue 11/10 Wed 11/11 Thu 11/12 Fri 11/13
InjSB
5a - 9a
BPM, Viewer, Wien Work BPM, Viewer, Wien, Harp Work BPM, Viewer, Wien, Harp Work BPM, Viewer, Wien, Harp Work Viewer, Wien, Harp Work
Tunnel
5a - 9a
Viewer Cable Pulls T INSTALL Pedestals, base pads, solenoid stand drilling INSTALL work
Viewer Cable Pulls
S&A Survey Pedestals
InjSB
9a - 12p
PSS Upgrade
BPM, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
BPM, Harp, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
BPM, Harp, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
BPM, Harp, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
Harp, Viewer, Wien Work
CIS Rack Work
Tunnel
9a - 12p
Viewer cable pulls S&A Sets New(er) Points
DC Power Resistor Box Button-Up
INSTALL Pedestals, base pads, solenoid stand drilling Viewer Cable Pulls
11a: Laser Safety System Audit
S&A Survey Pedestals
InjSB
12p - 4p
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
Tunnel
12p - 4p
M S&A Sets New(er) Points Cable pulls? R S&A Survey Pedestals

InjSB Week8.png

Week 9 (Nov 16 - Nov 20)

Non-Tunnel Work
  1. Continue preparing new Y-chamber
  2. A1/A2 cube assemblies - (2) for vacuum testing, (1) for magnet fit-up/testing
  3. Prebuncher -- RF testing/tuning
  4. Wien-mania! (high level schedule) =>
    • Review V-wien magnetic field mapping results and determine any remaining desired measurements
    • Finish V-wien field mapping and move to horizontal
    • Wien quad hardware arrivals?
    • Install HV switcher chassis
  5. 200kV PSS kicker fabrication
Tunnel work
  1. INSTALL grouts in pedestals (Mon/Tue) done?
  2. Fire pipe demo (Wed/Thur/Fri)
ISB Work
  1. Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos)
  2. PSS Upgrades -- now at many racks, from IN01B02->IN04B14, afternoons (Beizer)
  3. Viewer upgrades, IN03B07 (Norris)
  4. Harp upgrades, IN03B07 (Dela Cruz)
  5. CIS Rack Work, IN01B{00-05} (Windham)


Injector Tunnel and Service Building

Location
Time
Mon 11/16 Tue 11/17 Wed 11/18 Thu 11/19 Fri 11/20
InjSB
5a - 9a
Viewer, Harp, Wien Work Viewer, Harp, Wien Work Viewer, Harp, Wien Work Viewer, Harp, Wien Work Viewer, Harp, Wien Work
Tunnel
5a - 9a
INSTALL Grout pedestals T Fire pipe demo Fire pipe demo Lifting Plate Load Test
InjSB
9a - 12p
Viewer, Harp, Wien Work
CIS Rack Work
Viewer, Harp, Wien Work
CIS Rack Work
Harp, Viewer, Wien Work
CIS Rack Work
Harp, Viewer, Wien Work
CIS Rack Work
Harp, Viewer, Wien Work
CIS Rack Work
Tunnel
9a - 12p
INSTALL Grout pedestals Laser room/table work
Ceiling Lifting Plate Install
Fire pipe demo Fire pipe demo F
InjSB
12p - 4p
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
Tunnel
12p - 4p
M Laser room/table work Fire pipe demo Fire pipe demo F

InjSB Week9.png


Week 10 (Nov 23 - Nov 25 ๐Ÿฆƒ)

Non-Tunnel Work
  1. Complete assembly of new Y-chamber
  2. Magnetic mapping of spare aperture cube
  3. A1/A2 cube assemblies - (2) for vacuum testing, (1) for magnet fit-up/testing
  4. Prebuncher -- RF testing/tuning
  5. Wien-mania! (high level schedule) =>
    • Horizontal Wien magnetic assembly and field mapping
    • Bake V-wien electrode assembly with vacuum chamber
    • V-wien HV test at UITF
    • Resistor box testing at UITF?
Tunnel work
  1. Opportunistic cable pulls -- who wants to do some? Good week for it.
ISB Work
  1. Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos)
  2. PSS Upgrades -- now at many racks, from IN01B02->IN04B14, afternoons (Beizer)
  3. Viewer upgrades, IN03B07 (Norris)
  4. Harp upgrades, IN03B07 (Dela Cruz)
  5. CIS Rack Work, IN01B{00-05} (Windham)

Injector Tunnel and Service Building

Location
Time
Mon 11/23 Tue 11/24 Wed 11/25 Thu ๐Ÿฆƒ 11/26 Fri 11/27
InjSB
5a - 9a
Viewer, Harp, Wien Work Viewer, Harp, Wien Work Viewer, Harp, Wien Work
Tunnel
5a - 9a
M T W
InjSB
9a - 12p
Viewer, Harp, Wien Work
CIS Rack Work
Viewer, Harp, Wien Work
CIS Rack Work
Harp, Viewer, Wien Work
CIS Rack Work
Tunnel
9a - 12p
M T W
InjSB
12p - 4p
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
Tunnel
12p - 4p
M T W

InjSB Week9.png


Week 11 (Nov 30 - Dec 4)

Non-Tunnel Work
  • H-Wien
    • plate ready at shop, mic and test fit @ MMF
    • order (4) Ni plates
  • V-Wien
    • Start HV tests @ UITF
  • MHD
    • complete thermal test >2.5A
    • measure field profile and BL/I for CED
  • DR
    • measure DR per Jay's plan
  • A1/A2 cubes
    • complete assembly (coils + aperture), test motion and shorts
    • S&A fiducialize positions (stac5 A1=2/3/4 mm holes, manual A2=4/6/8 mm holes)
  • PSS kicker
    • vendor quotes?
    • place order
Tunnel work
  • Install
    • Y girder + 2I solenoid from 1137 to tunnel
    • Gun table to foot pads
  • S&A
    • Pre-align Y girder
    • Pre-align gun
  • PSS/CIS
    • Complete laser bypass
    • Align laser - test at window, viewer hole, cathode/flange
  • CIS/S&A
    • 2I solenoid on pedestal
    • 2I vacuum connection (valve to gun)
    • Final align
    • Final laser check
ISB Work
  • Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos)
  • PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
  • Viewer upgrades, IN03B{06-07} (Norris)
  • Harp upgrades, IN03B07 (Dela Cruz)
  • CIS Rack Work, IN01B{00-05} (Windham)


Injector Tunnel and Service Building

Location
Time
Mon 11/30 Tue 12/1 Wed 12/2 Thu 12/3 Fri 12/4
InjSB
5a - 9a
M T W R F
Tunnel
5a - 9a
M INSTALL: Y-chamber, solenoid PSS Laser Bypass Work S&A: Pre-align Gun-Y S&A: Pre-align Gun-Y
InjSB
9a - 12p
CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work
Tunnel
9a - 12p
M INSTALL: Y-chamber, solenoid CIS Laser Hut Work S&A: Pre-align Gun-Y S&A: Pre-align Gun-Y
CIS Laser Alignment Work
InjSB
12p - 4p
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
Tunnel
12p - 4p
M T W S&A: Pre-align Gun-Y S&A: Pre-align Gun-Y
CIS Laser Alignment Work

InjSB Week11.png

Week 12 (Dec 7 - Dec 11)

Non-Tunnel Work
  • Wien (Test Lab)
    • Test voltage divider box, calibrating UITF Matsusada HV PSs
    • U-Wien electrode alignment -- install teflon spacer (CIS), survey (S&A)
    • Improve V-wien electrode alignment? (S&A)
    • Receive Nickel endplates
  • A1/A2 cubes (Test Lab)
    • Test motion and shorts
    • Fiducialize positions (stac5 A1=2/3/4 mm holes, manual A2=4/6/8 mm holes) (S&A)
  • Prebuncher - high power testing
  • PSS kicker - build bids received, choosing one


  • MagTest
    • Wrapping up A2 measurements
    • Wrapping up A1 measurements


Tunnel work
  • Wien cable pulls? (Dela Cruz)
  • Laser alignment work (CIS)
  • Gun -> Y-chamber vacuum connections (CIS)
  • Viewer cable terminations (Norris)


ISB Work
  • Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos)
  • PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
  • Viewer upgrades, IN03B{06-07} (Norris)
  • Harp upgrades, IN03B07 (Dela Cruz)
  • CIS Rack Work, IN01B{00-05} (Windham)


Injector Tunnel and Service Building

Location
Time
Mon 12/7 Tue 12/8 Wed 12/9 Thu 12/10 Fri 12/11
InjSB
5a - 9a
M Viewer/Wien/Harp Work Viewer/Wien/Harp Work R F
Tunnel
5a - 9a
CIS Laser Work CIS Laser Work CIS Laser Work CIS Vaccum Connections? F
InjSB
9a - 12p
CIS Rack Work CIS Rack Work
Viewer/Wien/Harp Work
CIS Rack Work
Viewer/Wien/Harp Work
CIS Rack Work CIS Rack Work
Tunnel
9a - 12p
CIS Laser Work CIS Laser Work-
temp Vacuum Window Install
Facilities HVAC Investigation
CIS Laser Work R F
InjSB
12p - 4p
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
Tunnel
12p - 4p
CIS Laser Work CIS Laser Work
Facilities HVAC Investigation
CIS Laser Work R F


InjSB Week11.png


Week 13 (Dec 14 - Dec 18)

Non-Tunnel Work
  • MagTest
    • Measure DR per Jay's plan
    • QW field mapping
    • Once Ni plates installed, H-wien field mapping
Tunnel work
ISB Work

Week 14 (Dec 21 - Dec 23)

Non-Tunnel Work--
Tunnel work
  • Fire Pipe Installation
ISB Work

Penetration Work

InjSB Penetrations that are open (click for pictures): above laser hut, 58, 86, 108, 135

  • 34ft from floor of InjSB to floor of Inj tunnel
  • 25ft from floor of InjSB to elevated Inj tunnel cable tray

Penetration Cable Pulls/Removals --

  • Tony pulling new Wien E-field HV cables
  • Norris removing old Cat5 viewer cables
  • Norris pulling new viewer cables
  • Riad/Scott removing old Mott HV cables
  • Coleman pulling new Wien B-field magnet cables
  • Cole pulling new neutron detector cables (above 0L03)
  • Scott pulling motor control cables for A1++

InjSB Racks.png

Fire System Work

Description of Task: Replacement of tunnel sprinkler piping, fire alarm control panels in B85 & B98, replacement of detection devices.

update 11/9: 25% of demo completed
update 11/23: demo completed
update 12/8: fire pipe installation in Injector slated for Winter break ~12/21 - 1/3
"The drawings needed prior to fabrication of the INJ fire pipe have not gone through the system." No fire pipe install work over winter break.