Phase 1 Commissioning Schedule

From Ciswikidb
Revision as of 23:52, 29 June 2021 by Bruker (talk | contribs)
Jump to navigation Jump to search

Week 0, May 17th-23rd

Week 1, May 24th-30th

Week 2, May 31st🇺🇸 - June 6th

Week 3, June 7th-13th

Week 4, June 14th-20th

Week 5, June 21st-27th

Week 6, June 28th-July 4th

Collapse

Yan: tentatively available every day, DAY or SWING as needed.
Update 6/29: ILD HCO pending; sending beam there not expected until 7/9. However, the main machine is facing delays as well. There is understandable reluctance about staffing the MCC during the weekend (including Monday, observing 👽) if supporting the injector tasks is unnecessary in terms of being on time overall. We are therefore trying not to schedule anything for the weekend at this time.

OWL Shift Monday
6/28
Tuesday
6/29
Wednesday
6/30
Thursday
7/1
Friday
7/2
Saturday
7/3
Sunday
7/4 🇺🇸
Notes/Goals
Beam Commissioning
Plan (ATLis)
Continue 90° HWien w/ good transmission and auto-steer Mott Spot move and Wien setup for Mott measurement Wien setup Mott measurement Tentatively no staffing Tentatively no staffing ILD running
possible
once HCO
complete and
BA granted
Shift Leader Law Suleiman Law Law Law / /
Scientist #2 Suleiman / /
Crew Chief Law Law Law Law Forman Forman (?) Forman (?)
SSO Deir Deir Deir Deir Deir Garcia (?) Garcia (?)
DAY Shift 6/28 6/29 6/30 7/1 7/2 7/3 7/4 🇺🇸
Beam Commissioning
Plan (ATLis)
morning TBD; 12-24 Bunch length system check and measurement Heat and activate cathode 8-12 open; 12-16 beam recovery to FC2 Wien match Float or QCM characterization Tentatively no staffing Tentatively no staffing
Shift Leader morning TBD; 12-24 Kazimi Grames Kazimi Turner Wang / /
Scientist #2 12-24 Hofler; 12-16 Bruker Bruker Hofler Bruker? / /
Crew Chief Aiken Aiken Freeman Frierson Merz Merz (?) Merz (?)
SSO Gauthier Gauthier Gauthier Jones Jones Aiken (?) Aiken (?)
SWING Shift 6/28 6/29 6/30 7/1 7/2 7/3 7/4 🇺🇸
Beam Commissioning
Plan (ATLis)
12-24 Bunch length system check and measurement Heat and activate cathode (cont'd), no beam Bunch length setup Float or PQB if things work well PQB if things work well Tentatively no staffing Tentatively no staffing
Shift Leader 12-24 Kazimi Grames Kazimi Amali? Amali? / /
Scientist #2 12-24 Hofler Bruker? Bruker? / /
Crew Chief McCaughan McCaughan Moser Moser Moser Carlino (?) Carlino (?)
SSO Mock Mock Mock Mock Mock Anthony (?) Anthony (?)

Week 7, July 5th-July 11th

Week 8, July 12th-July 18th

High-Level View June 7th-July16th