UITF Fall 2022 Schedule
Jump to navigation
Jump to search
- Week 9/26
- MeV HCO continues...
- COMTRA install jobs complete by Fri. 9/28
- Week 10/3
keV beam in evenings (source, Mott, spin setups) start SRF cool down mid-week weekend
- MeV HCO/UITF complete by Fri. 10/6
- Take a short hiatus to clear head, re-charge batteries Sat/Sun
- ...or if someone has the oompf MeV HCO w/ beam begins
- Week of 10/10
Begin COMTRA
- ~3 days (6 shifts) for e-beam restore + x-ray setup + final align magnet/detector
- ~4 days (8 shifts) for polarimeter checkout + AP measurement + experiment systematic studies
- ... we go into weekend, try to wrap up...
- Week of 10/17
- End COMTRA as early in week as possible, say hard deadline by Tue or Wed...
- ...then vac work for leak check and weekend for pump down
- Week of 10/24
- Start KICKER
- ...10/26 represents 3 weeks of cold booster
- Week of 10/31
- End KICKER
- ...11/2 represents 4 weeks of cold booster
- ...SRF warm up
- Everything ends latest 11/4