- 16:58, 20 October 2020 diff hist +119 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 16:49, 20 October 2020 diff hist +43 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 16:37, 20 October 2020 diff hist +2 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 16:36, 20 October 2020 diff hist -2 CIS Phase 1 work plans
- 16:31, 20 October 2020 diff hist 0 N File:InjSB Week5.png current
- 16:19, 20 October 2020 diff hist +295 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 08:29, 20 October 2020 diff hist +363 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 18:21, 19 October 2020 diff hist +130 CEBAF Injector Upgrade →ATLIS Tasks
- 13:15, 19 October 2020 diff hist +142 CIS Phase 1 work plans →Fire System Work
- 13:10, 19 October 2020 diff hist +86 CIS Phase 1 work plans →Fire System Work
- 12:45, 19 October 2020 diff hist +26 CIS Phase 1 work plans
- 09:27, 16 October 2020 diff hist -35 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 08:59, 16 October 2020 diff hist +2 CIS Phase 1 work plans
- 17:10, 15 October 2020 diff hist 0 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23)
- 16:57, 15 October 2020 diff hist -14 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 16:55, 15 October 2020 diff hist -33 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23)
- 16:54, 15 October 2020 diff hist +9 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23)
- 16:54, 15 October 2020 diff hist -1 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23)
- 16:53, 15 October 2020 diff hist +306 CIS Phase 1 work plans
- 16:47, 15 October 2020 diff hist +414 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 09:07, 15 October 2020 diff hist +434 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 14:36, 14 October 2020 diff hist +111 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 14:25, 14 October 2020 diff hist +159 N Tunnel Photos Oct14 2020 Created page with " 1000px 1000px 1000px" current
- 14:22, 14 October 2020 diff hist +327 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 14:18, 14 October 2020 diff hist +1 CEBAF Injector Upgrade →Quick Links
- 14:17, 14 October 2020 diff hist 0 N File:Oct14 Chopper LookingUpstream.JPG current
- 14:17, 14 October 2020 diff hist 0 N File:Oct14 Ychamber LookingDownstream.JPG current
- 14:17, 14 October 2020 diff hist 0 N File:Oct14 Gun2 LookingDownstream.JPG current
- 14:13, 14 October 2020 diff hist +131 N Penetration135 Created page with "Entrance: IN03B17 Exit: Above middle of 0L03 cryomodule (first full zone) 1000px file:InjSB Racks.png"
- 14:12, 14 October 2020 diff hist +123 N Penetration108 Created page with "Entrance: IN03B04 Exit: Above harp IHA0L03, just before PSS fence 1000px file:InjSB Racks.png"
- 14:11, 14 October 2020 diff hist +121 N Penetration86 Created page with "Entrance: IN02B23 Exit: above MQJ0L02, just past plastic barrier 1000px file:InjSB Racks.png"
- 14:10, 14 October 2020 diff hist +107 N Penetration58 Created page with "Entrance: IN02B10 Exit: Above buncher cavity ~0I05 1000px File:InjSB Racks.png"
- 14:09, 14 October 2020 diff hist +1 PenetrationALH
- 14:08, 14 October 2020 diff hist +9 PenetrationALH
- 14:07, 14 October 2020 diff hist -1 PenetrationALH
- 14:06, 14 October 2020 diff hist +127 N PenetrationALH Created page with "Entrance: IN01B06 Exit: Above Laser hut, ~across for where Y-chamber would be. file:Pene108.JPG file:InjSB_Racks.png"
- 14:04, 14 October 2020 diff hist 0 N File:Pene108.JPG current
- 14:04, 14 October 2020 diff hist 0 N File:Pene135.JPG current
- 14:04, 14 October 2020 diff hist 0 N File:Pene86.JPG current
- 14:04, 14 October 2020 diff hist 0 N File:PeneLH.JPG current
- 14:04, 14 October 2020 diff hist 0 N File:Pene58.JPG current
- 13:58, 14 October 2020 diff hist +75 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 13:57, 14 October 2020 diff hist +2 CIS Phase 1 work plans
- 13:56, 14 October 2020 diff hist +156 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 13:51, 14 October 2020 diff hist 0 File:InjSB Racks.png Moser uploaded a new version of File:InjSB Racks.png current
- 13:50, 14 October 2020 diff hist 0 File:InjSB Racks.png Moser uploaded a new version of File:InjSB Racks.png
- 13:50, 14 October 2020 diff hist 0 File:InjSB Racks.png Moser uploaded a new version of File:InjSB Racks.png
- 09:05, 14 October 2020 diff hist +1 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 09:04, 14 October 2020 diff hist +445 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 17:00, 13 October 2020 diff hist +3 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23)