- 14:03, 21 October 2020 diff hist +1 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 09:33, 21 October 2020 diff hist -1 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 09:30, 21 October 2020 diff hist +3 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 09:30, 21 October 2020 diff hist +15 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 09:29, 21 October 2020 diff hist +3 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 09:28, 21 October 2020 diff hist +927 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 09:15, 21 October 2020 diff hist -69 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 18:39, 20 October 2020 diff hist +1 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 18:10, 20 October 2020 diff hist -3 CIS Phase 1 work plans
- 18:09, 20 October 2020 diff hist +1 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 18:08, 20 October 2020 diff hist +5 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 18:06, 20 October 2020 diff hist +34 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 18:03, 20 October 2020 diff hist +76 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 18:01, 20 October 2020 diff hist +664 CIS Phase 1 work plans
- 17:57, 20 October 2020 diff hist +774 CIS Phase 1 work plans
- 17:50, 20 October 2020 diff hist +1 CIS Phase 1 work plans
- 17:49, 20 October 2020 diff hist -1 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 17:48, 20 October 2020 diff hist -3 CIS Phase 1 work plans →Fire System Work
- 17:48, 20 October 2020 diff hist +1 CIS Phase 1 work plans →Fire System Work
- 17:45, 20 October 2020 diff hist +3 CIS Phase 1 work plans →Fire System Work
- 17:44, 20 October 2020 diff hist +129 CIS Phase 1 work plans
- 17:41, 20 October 2020 diff hist -17 CIS Phase 1 work plans →Penetration Work
- 17:41, 20 October 2020 diff hist +1 CIS Phase 1 work plans →Penetration Work
- 17:41, 20 October 2020 diff hist +16 CIS Phase 1 work plans →Penetration Work
- 17:40, 20 October 2020 diff hist 0 N File:Firepipe 10 Oct Update.docx current
- 17:40, 20 October 2020 diff hist +64 CIS Phase 1 work plans →Penetration Work
- 17:37, 20 October 2020 diff hist +1 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 17:36, 20 October 2020 diff hist +1,333 CIS Phase 1 work plans
- 17:30, 20 October 2020 diff hist +13 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 17:29, 20 October 2020 diff hist +36 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 17:27, 20 October 2020 diff hist -167 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 17:18, 20 October 2020 diff hist -23 CIS Phase 1 work plans
- 17:16, 20 October 2020 diff hist +190 CIS Phase 1 work plans
- 17:05, 20 October 2020 diff hist -22 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 17:04, 20 October 2020 diff hist 0 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 17:04, 20 October 2020 diff hist -9 CIS Phase 1 work plans →Week 1 (Sep 21 - Sep 27) High Voltage Testing w/ PSS lock-ups
- 17:01, 20 October 2020 diff hist -7 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 17:00, 20 October 2020 diff hist -82 CIS Phase 1 work plans
- 16:58, 20 October 2020 diff hist +119 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 16:49, 20 October 2020 diff hist +43 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 16:37, 20 October 2020 diff hist +2 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 16:36, 20 October 2020 diff hist -2 CIS Phase 1 work plans
- 16:31, 20 October 2020 diff hist 0 N File:InjSB Week5.png current
- 16:19, 20 October 2020 diff hist +295 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 08:29, 20 October 2020 diff hist +363 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 18:21, 19 October 2020 diff hist +130 CEBAF Injector Upgrade →ATLIS Tasks
- 13:15, 19 October 2020 diff hist +142 CIS Phase 1 work plans →Fire System Work
- 13:10, 19 October 2020 diff hist +86 CIS Phase 1 work plans →Fire System Work
- 12:45, 19 October 2020 diff hist +26 CIS Phase 1 work plans
- 09:27, 16 October 2020 diff hist -35 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild