- 10:09, 11 November 2020 diff hist +3 CIS Phase 1 work plans →Week 8 (Nov 9 - Nov 13) Beamline anchors/pedestals, Wien mapping/HV system, A1/A2 cubes, prebuncher
- 09:16, 11 November 2020 diff hist -34 CIS Phase 1 work plans →Week 8 (Nov 9 - Nov 13) Beamline anchors/pedestals, Wien mapping/HV system, A1/A2 cubes, prebuncher
- 10:07, 10 November 2020 diff hist +33 CIS Phase 1 work plans →Week 8 (Nov 9 - Nov 13) Beamline anchors/pedestals, Wien mapping/HV system, A1/A2 cubes, prebuncher
- 10:07, 10 November 2020 diff hist +127 CIS Phase 1 work plans →Week 8 (Nov 9 - Nov 13) Beamline anchors/pedestals, Wien mapping/HV system, A1/A2 cubes, prebuncher
- 09:00, 10 November 2020 diff hist +83 CIS Phase 1 work plans →Week 8 (Nov 9 - Nov 13) Beamline anchors/pedestals, Wien mapping/HV system, A1/A2 cubes, prebuncher
- 08:58, 10 November 2020 diff hist +39 CIS Phase 1 work plans →Week 8 (Nov 9 - Nov 13) Beamline anchors/pedestals, Wien mapping/HV system, A1/A2 cubes, prebuncher
- 08:40, 10 November 2020 diff hist 0 CIS Phase 1 work plans →Week 8 (Nov 9 - Nov 13) Beamline anchors/pedestals, Wien mapping/HV system, A1/A2 cubes, prebuncher
- 21:42, 9 November 2020 diff hist -2 CIS Phase 1 work plans →Week 8 (Nov 9 - Nov 13) Beamline anchors/pedestals, Wien mapping/HV system, A1/A2 cubes, prebuncher
- 21:39, 9 November 2020 diff hist 0 File:InjSB Week8.png Moser uploaded a new version of File:InjSB Week8.png current
- 21:36, 9 November 2020 diff hist +41 CIS Phase 1 work plans →Week 8 (Nov 9 - Nov 13) Beamline anchors/pedestals, Wien mapping/HV system, A1/A2 cubes, prebuncher
- 21:34, 9 November 2020 diff hist +4 CIS Phase 1 work plans →Week 8 (Nov 9 - Nov 13) Beamline anchors/pedestals, Wien mapping/HV system, A1/A2 cubes, prebuncher
- 21:33, 9 November 2020 diff hist 0 N File:InjSB Week8.png
- 21:07, 9 November 2020 diff hist +36 CIS Phase 1 work plans →Week 8 (Nov 9 - Nov 13) Beamline anchors/pedestals, Wien mapping/HV system, A1/A2 cubes, prebuncher
- 21:05, 9 November 2020 diff hist +81 CIS Phase 1 work plans →Week 9 (Nov 16 - Nov 20)
- 20:28, 9 November 2020 diff hist +124 CIS Phase 1 work plans →Week 8 (Nov 9 - Nov 13) Beamline anchors/pedestals, Wien mapping/HV system, A1/A2 cubes, prebuncher
- 20:27, 9 November 2020 diff hist -124 CIS Phase 1 work plans →Week 8 (Nov 9 - Nov 13) Beamline anchors/pedestals, Wien mapping/HV system, A1/A2 cubes, prebuncher
- 20:22, 9 November 2020 diff hist 0 CIS Phase 1 work plans →Week 8 (Nov 9 - Nov 13) Beamline anchors/pedestals, Wien mapping/HV system, A1/A2 cubes, prebuncher
- 20:22, 9 November 2020 diff hist 0 CIS Phase 1 work plans →Week 8 (Nov 9 - Nov 13) Beamline anchors/pedestals, Wien mapping/HV system, A1/A2 cubes, prebuncher
- 20:21, 9 November 2020 diff hist +1,440 CIS Phase 1 work plans
- 18:46, 30 October 2020 diff hist +12 CIS Phase 1 work plans →Week 7 (Nov 2 - Nov 6) Y-Chamber push, Diagnostics Upgrades
- 18:45, 30 October 2020 diff hist -52 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move Gun2 new location
- 18:20, 30 October 2020 diff hist -31 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move Gun2 new location
- 18:09, 30 October 2020 diff hist +13 CIS Phase 1 work plans →Week 7 (Nov 2 - Nov 6) Y-Chamber push, Diagnostics Upgrades
- 18:08, 30 October 2020 diff hist +158 CIS Phase 1 work plans →Week 7 (Nov 2 - Nov 6) Y-Chamber push, Diagnostics Upgrades
- 14:16, 30 October 2020 diff hist +45 CIS Phase 1 work plans →Week 7 (Nov 2 - Nov 6) Pedestal Point Layouts and Anchor Installs
- 14:13, 30 October 2020 diff hist 0 CIS Phase 1 work plans
- 13:04, 30 October 2020 diff hist +19 CIS Phase 1 work plans →Week 7 (Nov 2 - Nov 6) Pedestal Point Layouts and Anchor Installs
- 13:03, 30 October 2020 diff hist +107 CIS Phase 1 work plans →Week 7 (Nov 2 - Nov 6) Pedestal Point Layouts and Anchor Installs
- 13:01, 30 October 2020 diff hist -13 CIS Phase 1 work plans →Week 8 (Nov 9 - Nov 13)
- 13:01, 30 October 2020 diff hist -74 CIS Phase 1 work plans →Week 7 (Nov 2 - Nov 6) Pedestal Point Layouts and Anchor Installs
- 12:57, 30 October 2020 diff hist +13 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move Gun2 new location
- 10:56, 30 October 2020 diff hist -1 Historical Timeline →1993
- 10:55, 30 October 2020 diff hist +2 Historical Timeline →1993
- 10:55, 30 October 2020 diff hist +2 Historical Timeline →1993
- 10:55, 30 October 2020 diff hist +35 Historical Timeline
- 10:54, 30 October 2020 diff hist 0 N File:1993.png current
- 10:48, 30 October 2020 diff hist +94 CEBAF Injector Upgrade →ATLIS Tasks
- 09:42, 30 October 2020 diff hist +75 CIS Phase 1 work plans →Week 7 (Nov 2 - Nov 6) Pedestal Point Layouts and Anchor Installs
- 09:18, 30 October 2020 diff hist +4 CIS Phase 1 work plans →Week 7 (Nov 2 - Nov 6) Pedestal Point Layouts and Anchor Installs
- 08:21, 30 October 2020 diff hist +89 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move Gun2 new location
- 14:00, 29 October 2020 diff hist -1 CIS Phase 1 work plans
- 13:44, 29 October 2020 diff hist +19 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move Gun2 new location
- 13:40, 29 October 2020 diff hist 0 N File:InjSB Week7.png current
- 13:37, 29 October 2020 diff hist -195 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move Gun2 new location
- 13:28, 29 October 2020 diff hist +88 CIS Phase 1 work plans
- 13:27, 29 October 2020 diff hist +1,534 CIS Phase 1 work plans
- 13:17, 29 October 2020 diff hist 0 CIS Phase 1 work plans →Week 7 (Nov 2 - Nov 6) Pedestal Point Layouts and Anchor Installs
- 13:15, 29 October 2020 diff hist -16 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move Gun2 new location
- 13:15, 29 October 2020 diff hist +17 CIS Phase 1 work plans