- 13:11, 7 January 2021 diff hist +390 CIS Phase 1 work plans →Week 15 (Jan 11 - Jan 15)
- 13:07, 7 January 2021 diff hist +113 CIS Phase 1 work plans →Week 15 (Jan 11 - Jan 15)
- 11:00, 7 January 2021 diff hist +239 CIS Phase 1 work plans →Week 15 (Jan 11 - Jan 15)
- 10:08, 7 January 2021 diff hist +300 CIS Phase 1 work plans →Fire System Work
- 10:03, 7 January 2021 diff hist +96 CEBAF Injector Upgrade →ATLIS Tasks
- 20:18, 6 January 2021 diff hist +120 CEBAF Injector Upgrade →ATLIS Tasks
- 09:17, 6 January 2021 diff hist +122 CIS Phase 1 work plans →Week 14 (Jan 4 - Jan 8)
- 08:59, 5 January 2021 diff hist +25 CIS Phase 1 work plans →Week 14 (Jan 4 - Jan 8)
- 08:57, 5 January 2021 diff hist +73 CIS Phase 1 work plans →Week 14 (Jan 4 - Jan 8)
- 08:56, 5 January 2021 diff hist +164 CIS Phase 1 work plans →Week 14 (Jan 4 - Jan 8)
- 17:32, 4 January 2021 diff hist +96 CEBAF Injector Upgrade →ATLIS Tasks
- 17:29, 4 January 2021 diff hist 0 CIS Phase 1 work plans →Week 14 (Jan 4 - Jan 8)
- 17:28, 4 January 2021 diff hist 0 N File:InjSB Week14.png
- 09:18, 4 January 2021 diff hist +3 CIS Phase 1 work plans →Week 14 (Jan 4 - Jan 8)
- 09:17, 4 January 2021 diff hist +92 AIPINJ - Phase 1 and 2 Schedule
- 09:15, 4 January 2021 diff hist +825 CIS Phase 1 work plans →Week 14 (Jan 4 - Jan 8)
- 08:36, 4 January 2021 diff hist +1 CIS Phase 1 work plans →Week 14 (Jan 4 - Jan 8)
- 08:15, 4 January 2021 diff hist -2 CIS Phase 1 work plans →Week 14 (Jan 4 - Jan 8)
- 08:14, 4 January 2021 diff hist +242 CIS Phase 1 work plans →Week 14 (Jan 4 - Jan 8)
- 08:12, 4 January 2021 diff hist -1 CIS Phase 1 work plans →Week 13.6 (Dec 21 - Dec 23)
- 08:11, 4 January 2021 diff hist +2 CIS Phase 1 work plans
- 08:11, 4 January 2021 diff hist +1 CIS Phase 1 work plans
- 12:03, 18 December 2020 diff hist 0 CIS Phase 1 work plans
- 12:02, 18 December 2020 diff hist 0 CIS Phase 1 work plans
- 12:01, 18 December 2020 diff hist +2 CIS Phase 1 work plans →Week 13 (Dec 14 - Dec 18)
- 12:00, 18 December 2020 diff hist +13 CIS Phase 1 work plans →Week 13 (Dec 14 - Dec 18)
- 12:00, 18 December 2020 diff hist -79 CIS Phase 1 work plans →Week 13.6 (Dec 21 - Dec 23)
- 09:29, 18 December 2020 diff hist 0 CIS Phase 1 work plans →Week 13.6 (Dec 21 - Dec 23)
- 09:29, 18 December 2020 diff hist +9 N File:InjSB Week13.5.png dfasfasdf current
- 09:27, 18 December 2020 diff hist 0 File:InjSB Week13.6.png Moser uploaded a new version of File:InjSB Week13.6.png current
- 09:26, 18 December 2020 diff hist 0 File:InjSB Week13.6.png Moser uploaded a new version of File:InjSB Week13.6.png
- 09:26, 18 December 2020 diff hist 0 File:InjSB Week13.6.png Moser uploaded a new version of File:InjSB Week13.6.png
- 09:24, 18 December 2020 diff hist 0 File:InjSB Week13.6.png Moser uploaded a new version of File:InjSB Week13.6.png
- 09:21, 18 December 2020 diff hist +135 CIS Phase 1 work plans →Week 13.6 (Dec 21 - Dec 23)
- 08:07, 18 December 2020 diff hist +68 CIS Phase 1 work plans →Week 13 (Dec 14 - Dec 18)
- 14:31, 17 December 2020 diff hist -15 CIS Phase 1 work plans →Week 13.6 (Dec 21 - Dec 23)
- 14:30, 17 December 2020 diff hist +1 CIS Phase 1 work plans →Week 13.6 (Dec 21 - Dec 23)
- 14:29, 17 December 2020 diff hist 0 N File:InjSB Week13.6.png
- 14:15, 17 December 2020 diff hist 0 CIS Phase 1 work plans →Week 13.6 (Dec 21 - Dec 23)
- 14:15, 17 December 2020 diff hist -372 CIS Phase 1 work plans
- 12:02, 17 December 2020 diff hist +2 CIS Phase 1 work plans
- 12:01, 17 December 2020 diff hist -4 CIS Phase 1 work plans
- 11:47, 17 December 2020 diff hist -3 CIS Phase 1 work plans →Week 13.6 (Dec 21 - Dec 23)
- 11:47, 17 December 2020 diff hist +2 CIS Phase 1 work plans →Week 13.6 (Dec 21 - Dec 23)
- 11:46, 17 December 2020 diff hist +3 CIS Phase 1 work plans →Week 13.6 (Dec 21 - Dec 23)
- 11:46, 17 December 2020 diff hist -3 CIS Phase 1 work plans →Week 13.6 (Dec 21 - Dec 23)
- 11:46, 17 December 2020 diff hist -2 CIS Phase 1 work plans →Week 13.6 (Dec 21 - Dec 23)
- 11:45, 17 December 2020 diff hist +39 CIS Phase 1 work plans →Week 13.6 (Dec 21 - Dec 23)
- 11:44, 17 December 2020 diff hist +478 CIS Phase 1 work plans →Week 14 (Jan 4 - Jan 8)
- 11:34, 17 December 2020 diff hist +50 CIS Phase 1 work plans →Week 13.6 (Dec 21 - Dec 23)