- Measured QE ~ 3.5% with -100 V Gun bias. Was about 0.4% with -1 kV bias.
- Gun vacuum improved when opeening the gate valve to beamline – beamline vacuum went higher.
- Beam to F-Cup
- Plan to complete the second part of beamline in two weeks: plan for one-week down in about 2 weeks to install the second DP can, solenoid, ion precipitator and the BNNT diagnostic station.