GTS meeting 5 02 17
Jump to navigation
Jump to search
- Beta Calculations: media:Sajini_April2017_Beta_calculations.pdf
- Attempts to run at 1 mA:
- Ran for few seconds before a HV arc. QE dropped by a factor of 2.
- Ran again for 1.5 hours (with ion-precipitators on) before a HV arc. QE dropped by another factor of 2.
- ion collectors and anode current
- The downstream ion collector was wired incorrectly
- Cornell PRAB paper on ion clearing electrodes: Media:Cornell ion colelctors PhysRevAccelBeams.19.034201.pdf
- Down Monday - Wednesday to:
- Degas dump with NEGS at 25% on for ion pumps to take vacuum load
- Replace ND filter from ND1 to ND3
- Re-activate photocathode with 3 mm active area
- Instrument wire scanner
- Install WiFi access station and enable JMenu on PC in GTS cave
- Why is Dump/FC reading -20 nA?
- Hi-pot VIPGT06
- SCAM VL LINE SYNC frequency is not 60 Hz?
- Put ND filter in front of ITVGT06 and mount camera on the floor.