May 19, 2017 - 200kV gun upgrade meeting
Revision as of 19:21, 16 May 2017 by Grames (talk | contribs) (Created page with "===200kV Gun=== * Task and Timeline Gantt chart => media:170421_CHG.pdf ===Gun2 NEG Tube=== * Updated NEG tube => media:NEGTUBE_MAY03.pdf :M20 Old Assembly Modificati...")
200kV Gun
- Task and Timeline Gantt chart => media:170421_CHG.pdf
Gun2 NEG Tube
- Updated NEG tube => media:NEGTUBE_MAY03.pdf
- M20 Old Assembly Modification media:0990.pdf
- M20 New Assembly Can media:0991.pdf
- M20 New Assembly 6.00 x 4.500 reducer flangemedia:0.992.pdf
Gun3 Removal and Diagnostics Chamber Installation
- May 8-12 => Remove and replace Gun3 ATLIS task
Eliminating Gun Switch Software
- April 28 => Remove gun switch software ATLIS task
- Software removed and interlocks tested ELOG entry
- Yet to do a) remove VBV3I02 from special interlock and b) swap PLC for relays