Musts

1) CEBAF beam studies at high current, including DBR photocathode, and installation and testing of Brock's resonant polarimeter.

2) Other SAD activities and preparing for CEBAF operations

3) Recap what we decided to do regarding the installation of 200kV gun at CEBAF (i.e., delayed installation until next SAD)

4) Brief discussion of next SAD: ordering new glassman and stuff, designing the new baked beamline, 200kV Wien plans, and scheduling the Bubble Chamber exp.

5) UITF: making beam this summer? summer is half over. Other UITF business

6) GTS R&D: magnetized beam update, emittance confusion - are we clearing this up? Yan's thesis data, plans for 5mA operation, precipitator tests? planned installation of modelocked laser, the gain switched diode and fiber amplifier?

Shoulds

1) cryopumped vacuum study

2) vortex beams with miniMott

3) testing brock cavity as "kicker"

4) It does NOT seem like the NASA run will happen at LERF