UITF Meeting - January 24, 2018
Jump to navigation
Jump to search
- Shaun gave an update:
- Working on first MeV 80/20 stand layout and point (components may still be moved atop it)
- Provided Phil w/ DP can layout for assembly
- Will submit job to machine shop for (2) vertical chicane vacuum chambers
- Order add'l hardware right angle brackets (40) and 4-1/2" vee-blockes needed
- Phil/Marcy discussed count of components needs in MeV section, good news relatively list so far...
- Proceeding w Plan A 1.5" pipe w/ reducers as needed
- Would like to order additional IP's, with XHV IP near cryo-unit exit
- Too early for list of bolts/flanges
- Will begin building up the DP assembly
- Jim Kortze has the BCM cavity
- Joe updates
- CEBAF MeV region has quad upstream of DP station; for next week will evaluate beam envelope booster to chicane using Alicia's span of cases
- Positron spigot: Plan A is borrow 5D line from CEBAF, Plan B is reproduce those elements ... TBD
- Will suggest MeV corrector option that fits in 15" clear gap after each quad