The final stretch:

I&C
  • ion pumps along the MeV beamline, drop cables, junction boxes, epics screens for 14 more pumps
  • valves: per the song sheet, get them to work, air plumbing
  • viewers, pneumatic actuators, video
  • BPMs, we need them now
  • current monitoring at dumps, cups and apertures, water plumbing
  • harps
  • yao cavity, at least one needs to be installed, with electronics
Magnets