GTS meeting 2 11 19
Jump to navigation
Jump to search
List of completed beamline hardware modifications
- Replaced YAG screen on Viewer 1
- Replaced Slit on Viewer 2 with holes assembly
- Replaced two ion collectors with new ones
- Replaced Harp fork (Tony)
- Removed modified DP can
- Removed Faraday Cup
- Removed bellow upstream of dump
- Removed LDR Harp arm and replace with ion-pump
- Rotated Viewer 3 to vertical
- Installed TE011 Cavity
- Installed Deflecting Cavity
- Installed new 5th solenoid
- Moved DP can 1 to end of beamline
- All bellows at least 2.5 inch diameter
- Both gate valves are 2.5 inch-bore
- S&A on Thursday February 7, 2019
List of hardware support
- Install Deflecting Cavity power supply, MO and other parts
- Install TE011 Cavity readout cable and electronics
List of software and controls changes
- Re-program SCAM to allow for 1 Hz and 50 ns macro-pulses
- Add 5th solenoid to magnet screen