UITF Meeting - march 14, 2019

From Ciswikidb
Revision as of 07:35, 14 March 2019 by Poelker (talk | contribs) (Created page with "How about.....we dismantle the north pier that exists today, leaving the CMs in place. I'd prefer this happen days before the big job described below....because with north pe...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

How about.....we dismantle the north pier that exists today, leaving the CMs in place. I'd prefer this happen days before the big job described below....because with north peir removed, I can't make beam inside UITF


Then the new concrete blocks arrive for the piers, maybe they can get installed with CMs in place?


John moves the CMs


The long concrete chimney vent tile gets moved into place on top of the new piers


Next the SEG blocks get moved into place, with cantilever fixture, etc.,


The CMs can get moved back (this is a question)


Then we finish the north wall, secure the SEG blocks with steel structure. Can the extra concrete blocks on north wall get put into place with CMs on the roof? or do these concrete blocks need a cantilever arm too?