GTS meeting 8 12 19

From Ciswikidb
Revision as of 09:20, 12 August 2019 by Mstefani (talk | contribs)
Jump to navigation Jump to search
  • Overview:
    • RF power to voltage relation- Complete
    • See RF waveform "clipping"- complete (Need different optical link)
    • DC bias fix- needs bench testing
    • Quasi-bake of gun- complete
    • OSP- 8/6-8/7
    • HV processing- In progress
    • HV processing with solenoid on- sometime in the future
    • RF matching- sometime way in the future
  • Talking points:
    • HV Processing over the weekend
    • Krypton processing?
    • Double click on the dial; not around it
    • Optical-fiber link (need check voltage output of current unit and order)
    • Run without RF to have something for NAPAC (doesn't require DC Bias fix)