HDIce tile removal predictions: October 9, 2019

From Ciswikidb
Revision as of 12:41, 7 November 2019 by Poelker (talk | contribs)
Jump to navigation Jump to search

Andy's proposed run plan, the hard part is scheduling this work before May 2020. And lots of rooftop manipulations:

Run# 0 1 2 3 4 5
Objective IBC installation Booster Commissioning Aperture target/Empty Target Unpolarized Target Polarized Target Polarized Target
Tiles OFF and ON sequence OFF/ON
OFF/ON OFF/ON/OFF/ON OFF/ON/OFF/ON/OFF/ON OFF/ON/OFF/ON/OFF/ON
# times Neil visits the rooftop 2 (done) 0 2 4 6 6