HDIce tile removal predictions: October 9, 2019

From Ciswikidb
Revision as of 14:19, 7 November 2019 by Poelker (talk | contribs)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

(this page was updated November 7, 2019)

Andy's proposed run plan, the hard part is scheduling this work before May 2020. And lots of rooftop manipulations:

Run# X 0 1 2 3 4
Objective IBC installation Booster Commissioning Aperture target/Empty Target Unpolarized Target Polarized Target Polarized Target
Tiles OFF and ON sequence OFF/ON not required OFF/ON OFF/ON/OFF/ON OFF/ON/OFF/ON/OFF/ON OFF/ON/OFF/ON/OFF/ON
# times Neil visits the rooftop 2 (done) 0 2 4 6 6