GTS meeting 11/25/19
Safety:
- PSS: Certified
- GTS OSP: Signed
- Tgun OPS: Signed
Remaining Tasks:
- Fix viewers
- Connect first two corrector magnets
- Install PCB for remote bias control with John Musson
Timeline:
- Monday 25th- connect/test Magnets
- Tuesday 25th- install/test PCB
- Wednesday 27th- final checks on hot deck components
- 28th-1st- Long Thanksgiving weekend
- Monday 2nd- create first beam using radiation and vacuum as indicators