February 10, 2020 - Resource meeting
Jump to navigation
Jump to search
Announcements
- Mailing list launched => aipinj@jlab.org
- Latest layout update Friday Feb 10
Tally components by systems
Correctors
Bullets from last meeting...
- New 200kV small shed cathode electrode at machine shop (like electron at UITF)
- New gun 10" anode flange being designed to locate a steering coil closer to the gun
- Phil/Marcy starting to NEG coat vacuum chambers; need a 1kW sputtering PS that works (1 kV, 1 mA)
- PO for 200 kV injector solenoids written (delivery April - June)
- Shaun designed alignment fixture for new beam line solenoids
- PO for 200 kV Wien magnet coils written (delivery March)
- Success applying +/- 20kV to UITF Wien! Testing w/ better vacuum comes next...
- PO to be written for new 15 deg dipole next week
- Chase assigning new names for dipole and solenoids
- Starting to study which laser vacuum window to use 2-3/4" as-is, or 4-1/2"
- Curt waiting on kV spec for prebuncher @ 200 kV, for Watt in S.S. cavity
- Reza/Alicia/Dennis evaluating re-ordering of layout
- Looking at installing valve downstream of chopper #2 this down, possibly during fc#1 repair
- Gary Cheng inquiring about checking cryo lines between QCM and Booster
- 5D beam line will be removed
- Neil/Anthony working plan to build table to move QCM/Booster
ATLIS Tasks
AIPINJ
Non-AIPINJ
- New Gun2 loading chamber
- Placeholder for Tim Minga to test laser room smoke detector alarm to MCC/Guard
Quick links
Injector upgrade calendar
- Run (now - May 6)
- Phase 1 (May 6 - end of 2020)
- Run (Jan 2021 - Sep 13 2021)
- Phase 2 (Sep 13 - end of 2021)