Aug 26, 2020
Jump to navigation
Jump to search
- News
- CEBAF
- Any news from on-call?
- C goes to 1-pass for few days next week (Aug 31 - Sep 3) then returns
- LERF
- Andrei approved work at LERF to support the radio-isotope run
- Steve Benson's LERF punchlist media:200825_LERF_punchlist.docx
- Kevin's schedule media:200817_WAG.docx
- UITF
- Lock-up Thu/Fri for SRF Booster testing
- Matt is planning for Run 1 to begin on Mon Aug 31
- Safety
- Cat 2 PPE gear ordered for Joe, Bubba, Carlos, Marcy, Riad => pick-up on Thursday (otherwise 2 week delivery time)
- Cat 2 PPE size chart media:200825_CAT2PPE.jpg
- SAD/AIPINJ
- Preliminary layout rev. 4 complete media:SONGSHEET AUGUST 21 dm comments.pdf
- ME folders on M: contain complete drawings
- Budgets
- Marcy - many thanks for RSR vacuum estimates