Schedule between runs 1 and 2 at UITF

From Ciswikidb
Revision as of 13:12, 28 September 2020 by Poelker (talk | contribs) (Created page with " Hi Joe and Tony, I spoke to Cryo and Matt Poelker regarding our plans going forward for testing J11. The following is the agreed-upon schedule; this is essentially the same...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Hi Joe and Tony,

I spoke to Cryo and Matt Poelker regarding our plans going forward for testing J11. The following is the agreed-upon schedule; this is essentially the same as Allison's schedule, but allows for a delayed start due to cryo availability, and corrections for a weekend.

Tuesday, October 6th

   UITF and CMTF u-tube operations (u-tubes in the cave at 9:30am)
   J11 cooldown starting around noon
   VTA will not be able to draw, and Kinneys will be off; return and recovery will be operational
   Dewar fill rate lower while CM at 4K during the 24 hours soak
   J11 at 2K on the morning of Friday, October 9th


Wednesday, October 16th +/- 1 day

   Fast Cooldown (Cryo requires a decision on whether resources can be redirected from the 2K coldbox to do this)


Friday, October 23rd

   CMTF supply u-tube pulled
   CM warm-up started


Monday, October 26th

   U-tubes changed from CMTF to UITF; u-tubes pulled in CMTF
   VTA will not be able to draw, and Kinneys will be off; return and recovery will be operational
   UITF and VTA will be able to restart in the PM


Please let me know if you have any questions

Thanks, Naeem