CIS Phase 1 work plans
Week 1 (Sep 21 - Sep 27) High Voltage Testing w/ PSS lock-ups
- Updated schedule media:200914_AIPINJ_Weeks_Sep_18_update.docx
- High voltage test slides media:200902_HV_Plans.pptx
- Gun and Wien tasks Media:High Voltage Work Gun2 & Wien filters.xlsx
Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- Fri 9/25 - Mon 9/28
- CIS Gun Jobs
- Wien electrode testing – 9am!!!
- Gun HVPS lockout - DONE
- Gun HV cable disconnect – DONE
- Remove PIG – Coordinate w/ Neil for convenient time
- Shukui - Laser outrigger table as-founds, remove components
- Scott - Remove yellow box
- Scott - Disconnect Decarad
- Monday 9/28 Tasks (updated 0915 9/28)
- Power down Wein system (Scott/Joe)
- Power down and remove DecaRad system (Scott)
- Return gun valve config to "normal" (Marcy)
- Dispose of grey mineral oil tank in coordination w/ESH&Q (Carlos/Bubba)
- PSS Kickers and associated chassis removal (SSG)
- Laser table disassembly (Shukui/Scott)
- Tuesday 9/29 Tasks (updated 0930 9/29)
- (Done) Disconnect BPMs 2I01->0I02A (Pete) beginning 5a
- (Done) Disconnect aperture and cup signal cables (Pete) 5a
- Disconnect rad probes (Melvin) 8a
- Tunnel magnet disconnects (Diggs, Delk) 10a
- (Done) Removal of old chopper amps from rack (Farrish)
- Harp upgrade to PC104 (Dela Cruz)
- ODH Head Replacements (SSG)
- Document existing Wein cabling and power off PS (Scott)
- Wednesday 9/30 Tasks (updated 0900 9/30)
- RF Prebuncher disconnects (Farrish) 6a
- Vacuum Component Labeling (Greenfield, Gonzales) 430a
- Magnet disconnects -- wire wrap-ups, junction box investigation (Coleman, Diggs, Delk) 10a
- Tiny magnet removals (Scott, Grames) 9a
- PSS Kicker Magnet removal (SSG) 9a
- Sample hold cables install, InjSB (Francis)
- Remaining PSS Interface chassis removal (SSG)
- Harp upgrade to PC104 (Dela Cruz)
- Moser transfers CCOC phone @1430, to reach moving forward x5089
- Thursday 10/1 Tasks (updated 0830 10/1)
- Picoammeter Removal, InjSB (Francis) 5a
- Sample hold cables install, IN02B24 (Francis)
- BPM Work in IN02B2* (Francis)
- Chopper amplifier upgrade (Farrish)
- Harp upgrade to PC104 (Dela Cruz)
- Viewer+harp hardware disconnects (Norris, Dela Cruz) 6a
- Disconnecting water and air lines from apertures and cups (Adderley) 8a
- Mech Install Pre-Job Walk-Thru (Grames, Wilson) 9a
- Friday 10/2 Tasks (updated 0900 10/2)
- Viewer disconnects (Norris) 6a
- BPM Work in IN02B2* (Francis)
- Chopper amplifier upgrade (Farrish)
- Harp upgrade to PC104 (Dela Cruz)
- PSS Kicker Cables tie-up (SSG)
- Survey and Alignment control measure around gun (S&A)
- Load suitcase with "bad" pucks (CIS)
- Pump-down vacuum in front of tee for next week (CIS)
- Tunnel Work
Time | Mon 9/28 | Tue 9/29 | Wed 9/30 | Thu 10/1 | F 10/2 |
---|---|---|---|---|---|
4a - 8a | I&C; 5a: Francis: BPMs, Cups, Apertures | I&C; 430a: Greenfield + Gonzales: vacuum labelling; 6a: Farrish: Prebuncher | I&C; 6a: Norris: Viewer; 6a: Dela Cruz, Harps | I&C: Norris: Viewer disconnects | |
8a - 10a | CIS + SSG | RadCon: rad probes | SSG: Kicker magnet removal; CIS: Tiny magnet removals | CIS; Adderley: Aperture+Cups Air/Water; Grames: Mech Install Walk-Thru | S&A: Gun |
10a - 12p | CIS + SSG | DC Power | DC Power: Wire wrap-ups, junction box investigation | S&A: Gun; SSG: Kicker cable tie-up | |
12p - 2p | CIS + SSG | DC Power | DC Power: Wire wrap-ups, junction box investigation | DC Power | S&A: Gun |
2p - 4p | CIS + SSG | DC Power | 3p: Moser: Safety Warden checks | S&A: Gun | |
4p - ?? |
- Other Work Occurring When Convenient
- Remove suitcase, Tunnel (CIS)
- Harp upgrade, InjSB (I&C)
- ODH Head Replacement, InjSB and Tunnel (SSG)
- PSS Chassis Removals, InjSB (SSG)
Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- Monday Oct 5
- vacuum tests, disconnects, and pre-removal blank offs (CIS)
- QCM->downstream Survey and Alignment
- S&H cable work for iocinse4, InjSB (Francis)
- Tuesday Oct 6
- Survey and Alignment finishing up around 0L04 (S&A)
- U-tube operations at 0L03 (Cryo)
- S&H cable work for iocinse4, InjSB (Francis)
- Stage/prepare for craning our girders (Mech Install)
- Chopper SSA upgrade -- LCW line install, InjSB (Mech Install / RF)
- Wednesday Oct 7
- S&H cable work for iocinse4, InjSB (Francis)
- Chopper SSA upgrade, InjSB (Farrish)
- Wein PS Work, InjSB (Windham)
- VIP UHV PS Work, InjSB (Windham)
- Harp PC104 upgrade, InjSB (Dela Cruz)
- Thursday Oct 8
- BPM work, InjSB (Francis)
- Chopper SSA upgrade, InjSB (Farrish)
- Harp PC104 upgrade, InjSB (Dela Cruz)
- Wednesday Oct 7 and Thursday Oct 8 -- Mechanical Install
- Remove to test lab --
- Laser outrigger table
1st Wein girder and pedestals- 2nd Wein girder, apertures, and pedestals
Photocathode puck suitcase on cart
- Remove to Brett Lewis grey oil tank
- Penetration stone drops
Current list of Injector penetrations to be dropped: 57, 86, 108, possibly this one
Penetration drop distance e3854100:
- 34ft from floor of InjSB to floor of Inj tunnel
- 25ft from floor of InjSB to elevated Inj tunnel cable tray
- Friday Oct 9
- BPM Work, InjSB (Francis)
- Chopper SSA upgrade, InjSB (Farrish)
- Harp PC104 upgrade, InjSB (Dela Cruz)
- Penetration stone drop -- 57, 86, 108, Tunnel (Mech Install)
- Penetration above laser hut already opened
Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- Laser/Y-Chamber viewer for Y-chamber girder (Marcy)
- Fiducializing Y-chamber girder (S&A)
- Laser window under vacuum evaluations (Phil/Shukui/Caryn)
- Documenting early InjSB racks (Scott)
- Cable pulls through penetrations (EES)
Fire pipe demolition?(Facilities Contractor)- Wein upgrade (Carlos) --
- Finish new Wien electrodes drawing and sign-offs
- Vacuum chambers to machine shop for mods
- Begin creating new screens
- Injector Tunnel Photos from W 10/14
- Monday Oct 12
Tunnel --
- Hooking up VIPs to new 18V PS for load testing (Marcy/Scott)
- Cable pulls through penetrations (EES)
InjSB --
- BPM Cable Pulls through Penetration 86 (Francis)
- Chopper SSA upgrade (Farrish)
- Harp to PC104 upgrade (Dela Cruz)
- Early rack documentation and space optimization (Scott)
- PSS Upgrade work (IN02BNI, B29, B30) (SSG)
- Tuesday Oct 13
Tunnel --
- Cable pulls through penetrations (EES)
- Resistor box evaluation (Coleman)
InjSB --
- BPM Work, IN02B{*} (Francis)
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
- Harp to PC104 upgrade, IN03B07 (Dela Cruz)
- Early rack documentation and space optimization, IN01B{02-05} (Scott)
- PSS Upgrade, IN02{BNI, B29, B30} (SSG)
- Wednesday Oct 14
Tunnel --
- Cable pulls through penetrations (EES)
- Safety warden walk-through (Moser)
InjSB --
- BPM Work, IN02B{*} (Francis)
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
- Harp to PC104 upgrade, IN03B07 (Dela Cruz)
- Early rack documentation and space optimization, IN01B{02-05} (Scott)
- PSS Upgrade, IN02{BNI, B29, B30} (SSG)
- Determining rack location for Wien magnet PSs, IN02-middle (Coleman, Grames, Moser)
- Safety warden walk-through (Moser)
- Conduit in penetration 135 (Electricians)
- Thursday Oct 15
Tunnel --
- S&A Level surveys
InjSB --
- BPM Work, IN0{2,3}B{*} (Francis)
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
- Harp to PC104 upgrade, IN03B07 (Dela Cruz)
- Early rack documentation and space optimization, IN01B{02-05} (Scott)
- PSS Upgrade, IN02{BNI, B29, B30} (SSG)
- 20A PS Install, Rack re-org, IN02B22 (DC Power)
- Friday Oct 16
Tunnel --
- Cable pulls through penetrations (EES)
- Mott cable removals (Scott/Riad, EES)
InjSB --
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
- Harp to PC104 upgrade, IN03B07 (Dela Cruz)
- Early rack documentation and space optimization, IN01B{02-05} (Scott)
- PSS Upgrade, IN02{BNI, B29, B30} (SSG)
- 20A PS Install, Rack re-org, IN02B22 (DC Power)
- IN02B26 Power Lock-Out, ~915a (DC Power)
Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- Non-Tunnel Work
- Build new Y-chamber viewer => Y-built w/test screen, Laser being built.
- Use test screen + laser + S&A to verify position of first viewer => This week
- Install + align + vacuum seal (2) viewers => target this week
- Caryn will confirm but identified best ‘mushroom’ window, attach => done
- ME provide ALL points to S&A for installation (gun table, 2I stand, Y-chamber, 2 peds for Wien, 2 peds A1/A2) => ???
- Carlos' Wien-mania!
- Tunnel Work
- Complete remove old keV Mott cables => done
- Complete remove old gun HV cables => done
- Jim pulls Wien PS cables? => done
- Does Wien HV cable pull start? => starting this week
- Scott will finish tie back of cables on tunnel floor to cable tray => done
- Refill 86? => no, not yet
- Standing Injector Service Building Work
- BPM Work, IN0{2,3}B{*} (Francis)
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
- Harp to PC104 upgrade, IN03B07 (Dela Cruz)
- Early rack documentation and space optimization, IN01B{02-05} (Scott)
- PSS Upgrade, IN02{BNI, B29, B30} (SSG)
- 20A PS Install, Rack re-org, IN02B22 (DC Power)
- Monday Oct 19
Tunnel --
- Cryo u-tube pulls for 0L0{2,3,4}
- Tuesday Oct 20
Tunnel --
- Cable pulls and removals
InjSB --
- BPM Work, IN0{2,3}B{*} (Francis)
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
- Harp to PC104 upgrade, IN03B07 (Dela Cruz)
- Early rack documentation and space optimization, IN01B{02-05} (Scott)
- PSS Upgrade, IN02{BNI, B29, B30} (SSG)
- 20A PS Install, IN02B22, 2p - 4p (DC Power)
- Wednesday Oct 21
Tunnel --
- S&A Verify line with new control
InjSB --
- PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (SSG - single person)
- Viewer work, IN03B07, 6a - 9a (Norris)
- Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
- M56 Hardware Removal from IN02B22, (I&C)
- Thursday Oct 22
InjSB --
- Wien Magnet PS Install, IN02B22, afternoon (DC Power)
- Early rack documentation and space optimization, IN01B{00-05}, 9a - 4p (Windham)
- PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (SSG - single person)
- Viewer work, IN03B07, 6a - 9a (Norris)
- Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
- Friday Oct 23
Tunnel --
- Vacuum work clean room craned in 6a - 8a (Mech Install)
- Clean room setup and prepping (Marcy)
- Gun interlock checks in preparation of removal of old HV Interlock Chassis in IN01B02 (Windham, Grames)
- Laser room work (Shukui)
InjSB --
- Early rack documentation and space optimization, IN01B{00-05}, 9a - 4p (Windham)
- PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
- Viewer work, IN03B07, 6a - 9a (Norris)
- Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
- 20A PS Install, IN02B22 (DC Power)
Inj Service Building Work
Time | Wed 10/21 | Thu 10/22 | Fri 10/23 |
---|---|---|---|
5a - 9a | Dela Cruz, Norris, |
Dela Cruz, Norris, |
Dela Cruz, Norris, |
9a - 12p | |||
12p - 4p | DC Power, SSG, |
DC Power, SSG, Windham, |
DC Power, SSG, Windham, |
Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move Gun2 new location
- Tunnel work
- Remove NEG filter from HV chamber ✅
- Setup mobile cleanroom over HV chamber ✅
- Vent Gun3 chamber to test Gun3 valve ✅
- Vent Gun2 chamber to test Gun2 valve ✅
- Remove 2I NEG beam line, remove NEG pedestal (temporarily) ✅
- Replace 10” flange + SHV connector + blank off + pump down ✅
- Prep Gun3 & Y-chamber for Install to remove ✅
- Wrap up UHV ion pump power supply power tests ✅
- INSTALL lift and move gun table off feet, & move Gun3 & Y-chamber back to TL-1137 ✅
- S&A may start setting/checking points (gun feet, 2I ped, Y ped, Wien ped, A1/A2 ped) ✅
- Non-Tunnel Work
- Finish Y-chamber : add viewers, add laser vacuum window, add NEG towers, add gun valve on-going
- Wien-mania! (high level schedule)
- -Wien magnetic field mapping next couple weeks
- -Bubba assembles the fixtures ✅
Injector Tunnel and Service Building Work
Location Time |
Mon 10/26 | Tue 10/27 | Wed 10/28 | Thu 10/29 | Fri 10/30 |
---|---|---|---|---|---|
InjSB 5a - 9a |
Norris, Dela Cruz, Francis | Norris, Dela Cruz, Francis | Norris, Dela Cruz, Francis | Norris, Dela Cruz, Francis | Norris, Dela Cruz, Francis |
Tunnel 5a - 9a |
Gun Vacuum Work | Gun Vacuum Work | Gun2 Table Move Y-Chamber+Gun3 Removal |
||
InjSB 9a - 12p |
Francis, SSG | Francis, Windham, SSG | Francis, Windham, SSG | Dela Cruz, Norris, Francis, SSG | Francis, SSG |
Tunnel 9a - 12p |
Gun Vacuum Work | Gun Vacuum Work | 9a CIS+MechInstall Walk-Thru | Wien Cable Pulls | Cryo 0L02 L-tube pull Fire pipe walk thru S&A Point Layouts |
InjSB 12p - 4p |
SSG | Windham, SSG | Windham, SSG Trim Rack Checks |
SSG | SSG |
Tunnel 12p - 4p |
Gun Vacuum Work | Gun Vacuum Work 3p:Videographer Tour |
S&A Point Layouts |
- Mon Oct 26
Tunnel --
- Gun vacuum work, 9a - 4p (CIS)
InjSB --
- PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
- Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
- Viewer work, IN03B07, 6a - 9a (Norris)
- BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
- 20A Wien Magnet PS Install, IN02B22 (Coleman)
- LLRF air temperature control system removal from IN01B13? (Plawski?)
- Tues Oct 27
Tunnel --
- Gun vacuum work, 9a - 3p (CIS)
- Videographer Tour, 3p+ (K. Carter + two videographers)
InjSB --
- PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
- Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
- Viewer work, IN03B07, 6a - 9a (Norris)
- BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
- CIS Rack Work, IN01B{00-05} 9a - 4p (Windham)
- 20A Wien Magnet PS Install, IN02B22 (Coleman)
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
- LLRF air temperature control system removal from IN01B13? (Plawski?)
- Wed Oct 28
Tunnel --
- CIS + MechInstall Walk-Through of Gun Table Move, Removal of Gun3 stub and Y-chamber, 9a
InjSB --
- PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
- Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
- Viewer work, IN03B07, 6a - 9a (Norris)
- BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
- CIS Rack Work, IN01B{00-05} 9a - 4p (Windham)
- Trim Card Checks, IN02B{10+11+26} + IN04B10, 12p-1p (Richardson)
Other Possible Work....
- 20A Wien Magnet PS Install, IN02B22 (Coleman)
- Chopper SSA upgrade, back of IN01B{03-11}, (Farrish)
- Thur Oct 29
Tunnel --
- Gun2 move, 5a - 8a (Mech Install)
- Removal of Gun3 and Y-chamber to Test Lab, 5a - 8a (Mech Install)
- Wien HV and control cable pulls, 9a - 1p (Dela Cruz)
InjSB --
- PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
- Wien controls work, IN01B03, 6a - 1p (Dela Cruz)
- Viewer work, IN03B07, 6a - 1p (Norris)
- BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
Other possible work....
- 20A Wien Magnet PS Install, IN02B22 (Coleman)
- Chopper SSA upgrade, back of IN01B{03-11}, (Farrish)
- All Hallows' Eve Eve 👻 (Fri 10/30)
Tunnel --
- Cryo L-tube Removal from 0L02, 8a - 12p (Cryo)
- Fire pipe demo job walk-through, 12p (Grames, Suhring, Renzo)
- Point Layouts, after cryo (S&A)
InjSB --
- PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
- Wien controls work, IN01B03, 6a - 1p (Dela Cruz)
- Viewer work, IN03B07, 6a - 1p (Norris)
- BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
Other possible work....
- 20A Wien Magnet PS Install, IN02B22 (Coleman)
- Chopper SSA upgrade, back of IN01B{03-11}, (Farrish)
Week 7 (Nov 2 - Nov 6) Fire pipe removal, viewer design, modify existing pedestals, Wien filter mapping
Tunnel work
- Mon/Tue
- INSTALL crane support (move Y-girder, Gun3 chamber, anything else back to TL1137)
- CIS take opportunity to a) cover your stuff before fire pipe demo, b) clean up cabinets, toolbox
- EES-IC Cable Pulls, Termination, and Routing
- Wed/Thu and maybe Fri
- Fire pipe demolition
Non-Tunnel Work
- Complete Y-chamber: add viewers, add laser vacuum window, add NEG towers, add gun valve
- Wien-mania! (high level schedule) => H/V-wien magnetic field mapping
InjSB Work
- Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos) --
- Comm chassis to digiport server
- PSS Upgrade, IN02B{NI, 29, 30} (Beizer)
- Viewer work, IN03B0{6+7} (Norris)
- BPM Work, IN03B{05-08, 23} (Francis)
- CIS Rack Work, IN01B{00-05} (Windham)
Other possible work...
- 20A Wien Magnet PS Install (Coleman)
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
Injector Tunnel and Service Building
Location Time |
Mon 11/2 | Tue 11/3 Election Day 🇺🇸 |
Wed 11/4 | Thu 11/5 | Fri 11/6 |
---|---|---|---|---|---|
InjSB 5a - 9a |
BPM, Viewer, Wien Work | BPM, Viewer, Wien Work | BPM, Viewer, Wien Work | BPM, Viewer, Wien Work | BPM, Viewer, Wien Work |
Tunnel 5a - 9a |
Wien + viewer cable pulls INSTALL Crane Outs |
Wien + viewer cable pulls | Fire pipe demo | Fire pipe demo | F(riday) |
InjSB 9a - 12p |
PSS Upgrade BPM, Viewer, Wien Work CIS Rack Work |
PSS Upgrade BPM, Viewer, Wien Work CIS Rack Work |
PSS Upgrade BPM, Viewer, Wien Work CIS Rack Work |
PSS Upgrade BPM, Viewer, Wien Work CIS Rack Work |
PSS Upgrade BPM, Viewer, Wien Work CIS Rack Work |
Tunnel 9a - 12p |
Wien + viewer cable pulls | Wien + viewer cable pulls | Fire pipe demo | Fire pipe demo | F(loat) |
InjSB 12p - 4p |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
Tunnel 12p - 4p |
M | T | Fire pipe demo | Fire pipe demo | F |
Week 8 (Nov 9 - Nov 13) Install gun table anchors, pedestals, Wien mapping, Wien HV system, A1/A2 cubes, prebuncher
Tunnel work
- Mon/Tue - S&A is queued up to set new(er) gun foot pad points
- Tue/Wed - Shaun predicts 4 pedestals arrive, Jenord inspects them; other peds exist in tunnel - thank you Phil/Shaun!
- Thu/Fri - Install drills and drops anchors, prepare grout form?, maybe we return gun table (Tom, best guess for the fire pipe install?)
Non-Tunnel Work
- Wien-mania! (high level schedule)
- Complete Y-chamber build : laser window + (2) viewers + NEG Tower + Valve (gun3!?)
- Build HV Switcher box
- H/V-wien magnetic field mapping
- A1/A2 cube assemblies - (2) for vacuum testing, (1) for magnet fit-up/testing
- Prebuncher vacuum repair, leak check
- Submit PR for PSS kicker
InjSB Work
- Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos) --
- Wire HV PS
- Install Comm chassis
- PSS Upgrade, IN02B{NI, 29, 30} (Beizer)
- Viewer work, IN03B07 (Norris)
- BPM Work, IN03B{05-08, 23} (Francis)
- CIS Rack Work, IN01B{00-05} (Windham)
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
Week 9 (Nov 16 - Nov 20)
Non-Tunnel Work--
Tunnel work
InjSB Work
Week 10 (Nov 23 - Nov 25 🦃)
Non-Tunnel Work--
Tunnel work
InjSB Work
Penetration Work
InjSB Penetrations that are open (click for pictures): above laser hut, 58, 86, 108, 135
- 34ft from floor of InjSB to floor of Inj tunnel
- 25ft from floor of InjSB to elevated Inj tunnel cable tray
Penetration Cable Pulls/Removals --
- Tony pulling new Wien E-field HV cables
- Norris removing old Cat5 viewer cables
- Norris pulling new viewer cables
Riad/Scott removing old Mott HV cablesColeman pulling new Wien B-field magnet cables- Cole pulling new neutron detector cables (above 0L03)
Scott pulling motor control cables for A1++
Fire System Work
Description of Task: Replacement of tunnel sprinkler piping, fire alarm control panels in B85 & B98, replacement of detection devices.
Latest construction schedule has contractor in Injector between 11/24/20 and 1/4/21.