CIS Phase 1 work plans

From Ciswikidb
Jump to navigation Jump to search

2020 Weeks 1 through 13

Week 1 (Sep 21 - Sep 27) High Voltage Testing w/ PSS lock-ups

Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects

Fri 9/25 - Mon 9/28
  • CIS Gun Jobs
Wien electrode testing – 9am!!!
Gun HVPS lockout - DONE
Gun HV cable disconnect – DONE
Remove PIG – Coordinate w/ Neil for convenient time
Shukui - Laser outrigger table as-founds, remove components
Scott - Remove yellow box
Scott - Disconnect Decarad
Monday 9/28 Tasks (updated 0915 9/28)
  • Power down Wein system (Scott/Joe)
  • Power down and remove DecaRad system (Scott)
  • Return gun valve config to "normal" (Marcy)
  • Dispose of grey mineral oil tank in coordination w/ESH&Q (Carlos/Bubba)
  • PSS Kickers and associated chassis removal (SSG)
  • Laser table disassembly (Shukui/Scott)
Tuesday 9/29 Tasks (updated 0930 9/29)
  • (Done) Disconnect BPMs 2I01->0I02A (Pete) beginning 5a
  • (Done) Disconnect aperture and cup signal cables (Pete) 5a
  • Disconnect rad probes (Melvin) 8a
  • Tunnel magnet disconnects (Diggs, Delk) 10a
  • (Done) Removal of old chopper amps from rack (Farrish)
  • Harp upgrade to PC104 (Dela Cruz)
  • ODH Head Replacements (SSG)
  • Document existing Wein cabling and power off PS (Scott)
Wednesday 9/30 Tasks (updated 0900 9/30)
  • RF Prebuncher disconnects (Farrish) 6a
  • Vacuum Component Labeling (Greenfield, Gonzales) 430a
  • Magnet disconnects -- wire wrap-ups, junction box investigation (Coleman, Diggs, Delk) 10a
  • Tiny magnet removals (Scott, Grames) 9a
  • PSS Kicker Magnet removal (SSG) 9a
  • Sample hold cables install, InjSB (Francis)
  • Remaining PSS Interface chassis removal (SSG)
  • Harp upgrade to PC104 (Dela Cruz)
  • Moser transfers CCOC phone @1430, to reach moving forward x5089
Thursday 10/1 Tasks (updated 0830 10/1)
  • Picoammeter Removal, InjSB (Francis) 5a
  • Sample hold cables install, IN02B24 (Francis)
  • BPM Work in IN02B2* (Francis)
  • Chopper amplifier upgrade (Farrish)
  • Harp upgrade to PC104 (Dela Cruz)
  • Viewer+harp hardware disconnects (Norris, Dela Cruz) 6a
  • Disconnecting water and air lines from apertures and cups (Adderley) 8a
  • Mech Install Pre-Job Walk-Thru (Grames, Wilson) 9a
Friday 10/2 Tasks (updated 0900 10/2)
  • Viewer disconnects (Norris) 6a
  • BPM Work in IN02B2* (Francis)
  • Chopper amplifier upgrade (Farrish)
  • Harp upgrade to PC104 (Dela Cruz)
  • PSS Kicker Cables tie-up (SSG)
  • Survey and Alignment control measure around gun (S&A)
  • Load suitcase with "bad" pucks (CIS)
  • Pump-down vacuum in front of tee for next week (CIS)
Tunnel Work
Time Mon 9/28 Tue 9/29 Wed 9/30 Thu 10/1 F 10/2
4a - 8a I&C; 5a: Francis: BPMs, Cups, Apertures I&C; 430a: Greenfield + Gonzales: vacuum labelling; 6a: Farrish: Prebuncher I&C; 6a: Norris: Viewer; 6a: Dela Cruz, Harps I&C: Norris: Viewer disconnects
8a - 10a CIS + SSG RadCon: rad probes SSG: Kicker magnet removal; CIS: Tiny magnet removals CIS; Adderley: Aperture+Cups Air/Water; Grames: Mech Install Walk-Thru S&A: Gun
10a - 12p CIS + SSG DC Power DC Power: Wire wrap-ups, junction box investigation S&A: Gun; SSG: Kicker cable tie-up
12p - 2p CIS + SSG DC Power DC Power: Wire wrap-ups, junction box investigation DC Power S&A: Gun
2p - 4p CIS + SSG DC Power 3p: Moser: Safety Warden checks S&A: Gun
4p - ??
Other Work Occurring When Convenient
  • Remove suitcase, Tunnel (CIS)
  • Harp upgrade, InjSB (I&C)
  • ODH Head Replacement, InjSB and Tunnel (SSG)
  • PSS Chassis Removals, InjSB (SSG)

Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network

Monday Oct 5
  • vacuum tests, disconnects, and pre-removal blank offs (CIS)
  • QCM->downstream Survey and Alignment
  • S&H cable work for iocinse4, InjSB (Francis)
Tuesday Oct 6
  • Survey and Alignment finishing up around 0L04 (S&A)
  • U-tube operations at 0L03 (Cryo)
  • S&H cable work for iocinse4, InjSB (Francis)
  • Stage/prepare for craning our girders (Mech Install)
  • Chopper SSA upgrade -- LCW line install, InjSB (Mech Install / RF)
Wednesday Oct 7
  • S&H cable work for iocinse4, InjSB (Francis)
  • Chopper SSA upgrade, InjSB (Farrish)
  • Wein PS Work, InjSB (Windham)
  • VIP UHV PS Work, InjSB (Windham)
  • Harp PC104 upgrade, InjSB (Dela Cruz)
Thursday Oct 8
  • BPM work, InjSB (Francis)
  • Chopper SSA upgrade, InjSB (Farrish)
  • Harp PC104 upgrade, InjSB (Dela Cruz)
Wednesday Oct 7 and Thursday Oct 8 -- Mechanical Install
  • Remove to test lab --
    • Laser outrigger table
    • 1st Wein girder and pedestals
    • 2nd Wein girder, apertures, and pedestals
    • Photocathode puck suitcase on cart
  • Remove to Brett Lewis grey oil tank
  • Penetration stone drops

Current list of Injector penetrations to be dropped: 57, 86, 108, possibly this one

Penetration drop distance e3854100:

  • 34ft from floor of InjSB to floor of Inj tunnel
  • 25ft from floor of InjSB to elevated Inj tunnel cable tray
Friday Oct 9
  • BPM Work, InjSB (Francis)
  • Chopper SSA upgrade, InjSB (Farrish)
  • Harp PC104 upgrade, InjSB (Dela Cruz)
  • Penetration stone drop -- 57, 86, 108, Tunnel (Mech Install)
    • Penetration above laser hut already opened

Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild

  • Laser/Y-Chamber viewer for Y-chamber girder (Marcy)
  • Fiducializing Y-chamber girder (S&A)
  • Laser window under vacuum evaluations (Phil/Shukui/Caryn)
  • Documenting early InjSB racks (Scott)
  • Cable pulls through penetrations (EES)
  • Fire pipe demolition? (Facilities Contractor)
  • Wein upgrade (Carlos) --
    • Finish new Wien electrodes drawing and sign-offs
    • Vacuum chambers to machine shop for mods
    • Begin creating new screens
  • Injector Tunnel Photos from W 10/14


Monday Oct 12

Tunnel --

  • Hooking up VIPs to new 18V PS for load testing (Marcy/Scott)
  • Cable pulls through penetrations (EES)

InjSB --

  • BPM Cable Pulls through Penetration 86 (Francis)
  • Chopper SSA upgrade (Farrish)
  • Harp to PC104 upgrade (Dela Cruz)
  • Early rack documentation and space optimization (Scott)
  • PSS Upgrade work (IN02BNI, B29, B30) (SSG)


Tuesday Oct 13

Tunnel --

  • Cable pulls through penetrations (EES)
  • Resistor box evaluation (Coleman)

InjSB --

  • BPM Work, IN02B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)


Wednesday Oct 14

Tunnel --

  • Cable pulls through penetrations (EES)
  • Safety warden walk-through (Moser)

InjSB --

  • BPM Work, IN02B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • Determining rack location for Wien magnet PSs, IN02-middle (Coleman, Grames, Moser)
  • Safety warden walk-through (Moser)
  • Conduit in penetration 135 (Electricians)


Thursday Oct 15

Tunnel --

  • S&A Level surveys

InjSB --

  • BPM Work, IN0{2,3}B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • 20A PS Install, Rack re-org, IN02B22 (DC Power)
Friday Oct 16

Tunnel --

  • Cable pulls through penetrations (EES)
  • Mott cable removals (Scott/Riad, EES)

InjSB --

  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • 20A PS Install, Rack re-org, IN02B22 (DC Power)
  • IN02B26 Power Lock-Out, ~915a (DC Power)

Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation

Non-Tunnel Work
  • Build new Y-chamber viewer => Y-built w/test screen, Laser being built.
  • Use test screen + laser + S&A to verify position of first viewer => This week
  • Install + align + vacuum seal (2) viewers => target this week
  • Caryn will confirm but identified best β€˜mushroom’ window, attach => done
  • ME provide ALL points to S&A for installation (gun table, 2I stand, Y-chamber, 2 peds for Wien, 2 peds A1/A2) => ???
  • Carlos' Wien-mania!
Tunnel Work
  • Complete remove old keV Mott cables => done
  • Complete remove old gun HV cables => done
  • Jim pulls Wien PS cables? => done
  • Does Wien HV cable pull start? => starting this week
  • Scott will finish tie back of cables on tunnel floor to cable tray => done
  • Refill 86? => no, not yet
Standing Injector Service Building Work
  • BPM Work, IN0{2,3}B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • 20A PS Install, Rack re-org, IN02B22 (DC Power)
Monday Oct 19

Tunnel --

  • Cryo u-tube pulls for 0L0{2,3,4}
Tuesday Oct 20

Tunnel --

  • Cable pulls and removals

InjSB --

  • BPM Work, IN0{2,3}B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • 20A PS Install, IN02B22, 2p - 4p (DC Power)
Wednesday Oct 21

Tunnel --

  • S&A Verify line with new control

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (SSG - single person)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
  • M56 Hardware Removal from IN02B22, (I&C)


Thursday Oct 22

InjSB --

  • Wien Magnet PS Install, IN02B22, afternoon (DC Power)
  • Early rack documentation and space optimization, IN01B{00-05}, 9a - 4p (Windham)
  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (SSG - single person)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)


Friday Oct 23

Tunnel --

  • Vacuum work clean room craned in 6a - 8a (Mech Install)
  • Clean room setup and prepping (Marcy)
  • Gun interlock checks in preparation of removal of old HV Interlock Chassis in IN01B02 (Windham, Grames)
  • Laser room work (Shukui)

InjSB --

  • Early rack documentation and space optimization, IN01B{00-05}, 9a - 4p (Windham)
  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
  • 20A PS Install, IN02B22 (DC Power)


Inj Service Building Work

InjSB Racks.png

Time Wed 10/21 Thu 10/22 Fri 10/23
5a - 9a Dela Cruz, Norris, Francis Dela Cruz, Norris, Francis Dela Cruz, Norris, Francis
9a - 12p Francis, SSG, Windham Francis, SSG Francis, SSG, Windham
12p - 4p DC Power, SSG, Windham, Francis DC Power, SSG, Windham, Francis DC Power, SSG, Windham, Francis

Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move Gun2 new location

Tunnel work
  • Remove NEG filter from HV chamber βœ…
  • Setup mobile cleanroom over HV chamber βœ…
  • Vent Gun3 chamber to test Gun3 valve βœ…
  • Vent Gun2 chamber to test Gun2 valve βœ…
  • Remove 2I NEG beam line, remove NEG pedestal (temporarily) βœ…
  • Replace 10” flange + SHV connector + blank off + pump down βœ…
  • Prep Gun3 & Y-chamber for Install to remove βœ…
  • Wrap up UHV ion pump power supply power tests βœ…
  • INSTALL lift and move gun table off feet, & move Gun3 & Y-chamber back to TL-1137 βœ…
  • S&A may start setting/checking points (gun feet, 2I ped, Y ped, Wien ped, A1/A2 ped) βœ…
Non-Tunnel Work
  • Finish Y-chamber : add viewers, add laser vacuum window, add NEG towers, add gun valve on-going
  • Wien-mania! (high level schedule)
-Wien magnetic field mapping next couple weeks
-Bubba assembles the fixtures βœ…


Injector Tunnel and Service Building Work

Location
Time
Mon 10/26 Tue 10/27 Wed 10/28 Thu 10/29 Fri 10/30
InjSB
5a - 9a
Norris, Dela Cruz, Francis Norris, Dela Cruz, Francis Norris, Dela Cruz, Francis Norris, Dela Cruz, Francis Norris, Dela Cruz, Francis
Tunnel
5a - 9a
Gun Vacuum Work Gun Vacuum Work Gun2 Table Move
Y-Chamber+Gun3 Removal
InjSB
9a - 12p
Francis, SSG Francis, Windham, SSG Francis, Windham, SSG Dela Cruz, Norris, Francis, SSG Francis, SSG
Tunnel
9a - 12p
Gun Vacuum Work Gun Vacuum Work 9a CIS+MechInstall Walk-Thru Wien Cable Pulls Cryo 0L02 L-tube pull
Fire pipe walk thru
S&A Point Layouts
InjSB
12p - 4p
SSG Windham, SSG Windham, SSG
Trim Rack Checks
SSG SSG
Tunnel
12p - 4p
Gun Vacuum Work Gun Vacuum Work
3p:Videographer Tour
S&A Point Layouts

InjSB Week6.png


Mon Oct 26

Tunnel --

  • Gun vacuum work, 9a - 4p (CIS)

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
  • 20A Wien Magnet PS Install, IN02B22 (Coleman)
  • LLRF air temperature control system removal from IN01B13? (Plawski?)
Tues Oct 27

Tunnel --

  • Gun vacuum work, 9a - 3p (CIS)
  • Videographer Tour, 3p+ (K. Carter + two videographers)

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
  • CIS Rack Work, IN01B{00-05} 9a - 4p (Windham)
  • 20A Wien Magnet PS Install, IN02B22 (Coleman)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • LLRF air temperature control system removal from IN01B13? (Plawski?)
Wed Oct 28

Tunnel --

  • CIS + MechInstall Walk-Through of Gun Table Move, Removal of Gun3 stub and Y-chamber, 9a

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
  • CIS Rack Work, IN01B{00-05} 9a - 4p (Windham)
  • Trim Card Checks, IN02B{10+11+26} + IN04B10, 12p-1p (Richardson)

Other Possible Work....

  • 20A Wien Magnet PS Install, IN02B22 (Coleman)
  • Chopper SSA upgrade, back of IN01B{03-11}, (Farrish)


Thur Oct 29

Tunnel --

  • Gun2 move, 5a - 8a (Mech Install)
  • Removal of Gun3 and Y-chamber to Test Lab, 5a - 8a (Mech Install)
  • Wien HV and control cable pulls, 9a - 1p (Dela Cruz)

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Wien controls work, IN01B03, 6a - 1p (Dela Cruz)
  • Viewer work, IN03B07, 6a - 1p (Norris)
  • BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)

Other possible work....

  • 20A Wien Magnet PS Install, IN02B22 (Coleman)
  • Chopper SSA upgrade, back of IN01B{03-11}, (Farrish)
All Hallows' Eve Eve πŸ‘» (Fri 10/30)

Tunnel --

  • Cryo L-tube Removal from 0L02, 8a - 12p (Cryo)
  • Fire pipe demo job walk-through, 12p (Grames, Suhring, Renzo)
  • Point Layouts, after cryo (S&A)

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Wien controls work, IN01B03, 6a - 1p (Dela Cruz)
  • Viewer work, IN03B07, 6a - 1p (Norris)
  • BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)

Other possible work....

  • 20A Wien Magnet PS Install, IN02B22 (Coleman)
  • Chopper SSA upgrade, back of IN01B{03-11}, (Farrish)

Week 7 (Nov 2 - Nov 6)

Fire pipe removal, viewer design, modify existing pedestals, Wien filter mapping

Tunnel work
Mon/Tue
  1. INSTALL crane support (move Y-girder, Gun3 chamber, anything else back to TL1137)
  2. CIS take opportunity to a) cover your stuff before fire pipe demo, b) clean up cabinets, toolbox
  3. EES-IC Cable Pulls, Termination, and Routing
Wed/Thu and maybe Fri
  1. Fire pipe demolition
Non-Tunnel Work
  • Complete Y-chamber: add viewers, add laser vacuum window, add NEG towers, add gun valve
  • Wien-mania! (high level schedule) => H/V-wien magnetic field mapping
InjSB Work
  • Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos) --
    • Comm chassis to digiport server
  • PSS Upgrade, IN02B{NI, 29, 30} (Beizer)
  • Viewer work, IN03B0{6+7} (Norris)
  • BPM Work, IN03B{05-08, 23} (Francis)
  • CIS Rack Work, IN01B{00-05} (Windham)

Other possible work...

  • 20A Wien Magnet PS Install (Coleman)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)

Injector Tunnel and Service Building

Location
Time
Mon 11/2 Tue 11/3
Election Day πŸ‡ΊπŸ‡Έ
Wed 11/4 Thu 11/5 Fri 11/6
InjSB
5a - 9a
BPM, Viewer, Wien Work BPM, Viewer, Wien Work BPM, Viewer, Wien Work BPM, Viewer, Wien Work BPM, Viewer, Wien Work
Tunnel
5a - 9a
Wien + viewer cable pulls
INSTALL Crane Outs
Wien + viewer cable pulls Fire pipe demo Fire pipe demo F(riday)
InjSB
9a - 12p
PSS Upgrade
BPM, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
BPM, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
BPM, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
BPM, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
BPM, Viewer, Wien Work
CIS Rack Work
Tunnel
9a - 12p
Wien + viewer cable pulls Wien + viewer cable pulls Fire pipe demo Fire pipe demo F(loat)
InjSB
12p - 4p
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
Tunnel
12p - 4p
M T Fire pipe demo Fire pipe demo F

InjSB Week7.png

Week 8 (Nov 9 - Nov 13) Beamline anchors/pedestals, Wien mapping/HV system, A1/A2 cubes, prebuncher

Tunnel work
  1. Tue - S&A is queued up to set new(er) gun foot pad points
  2. Tue/Wed - Shaun predicts 4 pedestals arrive, Jenord inspects them; other peds exist in tunnel - thank you Phil/Shaun!
  3. Wed/Thu/Fri - Install drills and drops anchors, prepare grout form?, maybe we return gun table (Tom, best guess for the fire pipe install?)
ME work
  • S&A drop revised points for table base pads. ECD 11/10. done
  • 2I solenoid – done
SG print full size drill template for Neil.
Check fit of template.
  • Neil – Drill holes into top of solenoid stand (existing item and is currently in place) using drill template provided by Shaun. done
  • Neil drill anchor holes in floor done
HVC table base pads. done
Wien Girder Pedestals. done
Aperture Girder Pedestals. done
Details have been provided to Neil. done
  • Y chamber girder
Design new v-block mounting for Y & ion pump due to angle change of Y.
Fabricate or modifications.
Non-Tunnel Work
  1. Wien-mania! (high level schedule) - Wien magnet mapping, HVPS system controls (ADC/DAC), Switchbox build
  2. Complete Y-chamber build : laser window + (2) viewers + NEG Tower + Valve (gun3!?)
  3. A1/A2 cube assemblies - (2) for vacuum testing, (1) for magnet fit-up/testing
  4. Prebuncher vacuum repair, leak check
  • Did the leak check braze joint happen?
  • Did a final probe port length get decided?
  • Can we resolve these question, repair the probe port, clean, ready for testing by Friday?
  1. Submit PR for PSS kicker
ISB Work
  1. Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos) --
    • Wire HV PS
    • Install Comm chassis
  2. PSS Upgrade, IN02B{NI, 29, 30} (Beizer)
  3. Viewer upgrades, IN03B07 (Norris)
  4. Harp upgrades, IN03B07 (Dela Cruz)
  5. BPM Work, IN03B{05-08, 23} (Francis) Phase I: βœ…; jump-start on Phase II βœ…
  6. CIS Rack Work, IN01B{00-05} (Windham)
  7. Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  8. First Aid Cabinet re-stocks, back wall behind IN02B22ish + bottom of access stairs, (Occ Med + vendor), date TBD

Injector Tunnel and Service Building

Location
Time
Mon 11/9 Tue 11/10 Wed 11/11 Thu 11/12 Fri 11/13
InjSB
5a - 9a
BPM, Viewer, Wien Work BPM, Viewer, Wien, Harp Work BPM, Viewer, Wien, Harp Work BPM, Viewer, Wien, Harp Work Viewer, Wien, Harp Work
Tunnel
5a - 9a
Viewer Cable Pulls T INSTALL Pedestals, base pads, solenoid stand drilling INSTALL work
Viewer Cable Pulls
S&A Survey Pedestals
InjSB
9a - 12p
PSS Upgrade
BPM, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
BPM, Harp, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
BPM, Harp, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
BPM, Harp, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
Harp, Viewer, Wien Work
CIS Rack Work
Tunnel
9a - 12p
Viewer cable pulls S&A Sets New(er) Points
DC Power Resistor Box Button-Up
INSTALL Pedestals, base pads, solenoid stand drilling Viewer Cable Pulls
11a: Laser Safety System Audit
S&A Survey Pedestals
InjSB
12p - 4p
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
Tunnel
12p - 4p
M S&A Sets New(er) Points Cable pulls? R S&A Survey Pedestals

InjSB Week8.png

Week 9 (Nov 16 - Nov 20)

Non-Tunnel Work
  1. Continue preparing new Y-chamber
  2. A1/A2 cube assemblies - (2) for vacuum testing, (1) for magnet fit-up/testing
  3. Prebuncher -- RF testing/tuning
  4. Wien-mania! (high level schedule) =>
    • Review V-wien magnetic field mapping results and determine any remaining desired measurements
    • Finish V-wien field mapping and move to horizontal
    • Wien quad hardware arrivals?
    • Install HV switcher chassis
  5. 200kV PSS kicker fabrication
Tunnel work
  1. INSTALL grouts in pedestals (Mon/Tue) done?
  2. Fire pipe demo (Wed/Thur/Fri)
ISB Work
  1. Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos)
  2. PSS Upgrades -- now at many racks, from IN01B02->IN04B14, afternoons (Beizer)
  3. Viewer upgrades, IN03B07 (Norris)
  4. Harp upgrades, IN03B07 (Dela Cruz)
  5. CIS Rack Work, IN01B{00-05} (Windham)


Injector Tunnel and Service Building

Location
Time
Mon 11/16 Tue 11/17 Wed 11/18 Thu 11/19 Fri 11/20
InjSB
5a - 9a
Viewer, Harp, Wien Work Viewer, Harp, Wien Work Viewer, Harp, Wien Work Viewer, Harp, Wien Work Viewer, Harp, Wien Work
Tunnel
5a - 9a
INSTALL Grout pedestals T Fire pipe demo Fire pipe demo Lifting Plate Load Test
InjSB
9a - 12p
Viewer, Harp, Wien Work
CIS Rack Work
Viewer, Harp, Wien Work
CIS Rack Work
Harp, Viewer, Wien Work
CIS Rack Work
Harp, Viewer, Wien Work
CIS Rack Work
Harp, Viewer, Wien Work
CIS Rack Work
Tunnel
9a - 12p
INSTALL Grout pedestals Laser room/table work
Ceiling Lifting Plate Install
Fire pipe demo Fire pipe demo F
InjSB
12p - 4p
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
Tunnel
12p - 4p
M Laser room/table work Fire pipe demo Fire pipe demo F

InjSB Week9.png


Week 10 (Nov 23 - Nov 25 πŸ¦ƒ)

Non-Tunnel Work
  1. Complete assembly of new Y-chamber
  2. Magnetic mapping of spare aperture cube
  3. A1/A2 cube assemblies - (2) for vacuum testing, (1) for magnet fit-up/testing
  4. Prebuncher -- RF testing/tuning
  5. Wien-mania! (high level schedule) =>
    • Horizontal Wien magnetic assembly and field mapping
    • Bake V-wien electrode assembly with vacuum chamber
    • V-wien HV test at UITF
    • Resistor box testing at UITF?
Tunnel work
  1. Opportunistic cable pulls -- who wants to do some? Good week for it.
ISB Work
  1. Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos)
  2. PSS Upgrades -- now at many racks, from IN01B02->IN04B14, afternoons (Beizer)
  3. Viewer upgrades, IN03B07 (Norris)
  4. Harp upgrades, IN03B07 (Dela Cruz)
  5. CIS Rack Work, IN01B{00-05} (Windham)

Injector Tunnel and Service Building

Location
Time
Mon 11/23 Tue 11/24 Wed 11/25 Thu πŸ¦ƒ 11/26 Fri 11/27
InjSB
5a - 9a
Viewer, Harp, Wien Work Viewer, Harp, Wien Work Viewer, Harp, Wien Work
Tunnel
5a - 9a
M T W
InjSB
9a - 12p
Viewer, Harp, Wien Work
CIS Rack Work
Viewer, Harp, Wien Work
CIS Rack Work
Harp, Viewer, Wien Work
CIS Rack Work
Tunnel
9a - 12p
M T W
InjSB
12p - 4p
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
Tunnel
12p - 4p
M T W

InjSB Week9.png


Week 11 (Nov 30 - Dec 4)

Non-Tunnel Work
  • H-Wien
    • plate ready at shop, mic and test fit @ MMF
    • order (4) Ni plates
  • V-Wien
    • Start HV tests @ UITF
  • MHD
    • complete thermal test >2.5A
    • measure field profile and BL/I for CED
  • DR
    • measure DR per Jay's plan
  • A1/A2 cubes
    • complete assembly (coils + aperture), test motion and shorts
    • S&A fiducialize positions (stac5 A1=2/3/4 mm holes, manual A2=4/6/8 mm holes)
  • PSS kicker
    • vendor quotes?
    • place order
Tunnel work
  • Install
    • Y girder + 2I solenoid from 1137 to tunnel
    • Gun table to foot pads
  • S&A
    • Pre-align Y girder
    • Pre-align gun
  • PSS/CIS
    • Complete laser bypass
    • Align laser - test at window, viewer hole, cathode/flange
  • CIS/S&A
    • 2I solenoid on pedestal
    • 2I vacuum connection (valve to gun)
    • Final align
    • Final laser check
ISB Work
  • Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos)
  • PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
  • Viewer upgrades, IN03B{06-07} (Norris)
  • Harp upgrades, IN03B07 (Dela Cruz)
  • CIS Rack Work, IN01B{00-05} (Windham)


Injector Tunnel and Service Building

Location
Time
Mon 11/30 Tue 12/1 Wed 12/2 Thu 12/3 Fri 12/4
InjSB
5a - 9a
M T W R F
Tunnel
5a - 9a
M INSTALL: Y-chamber, solenoid PSS Laser Bypass Work S&A: Pre-align Gun-Y S&A: Pre-align Gun-Y
InjSB
9a - 12p
CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work
Tunnel
9a - 12p
M INSTALL: Y-chamber, solenoid CIS Laser Hut Work S&A: Pre-align Gun-Y S&A: Pre-align Gun-Y
CIS Laser Alignment Work
InjSB
12p - 4p
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
Tunnel
12p - 4p
M T W S&A: Pre-align Gun-Y S&A: Pre-align Gun-Y
CIS Laser Alignment Work

InjSB Week11.png

Week 12 (Dec 7 - Dec 11)

Non-Tunnel Work
  • Wien (Test Lab)
    • Test voltage divider box, calibrating UITF Matsusada HV PSs done, opted to use FLUKE 1000:1 V-probe and RMS true-value multimeter
    • U-Wien electrode alignment -- install teflon spacer (CIS) first-pass done, after discussions, may refine
    • Improve V-wien electrode alignment? (S&A) deferred
    • Receive Nickel endplates received, returned after finish found scratched, received again?
  • A1/A2 cubes (Test Lab)
    • Assemble fixture mounting plates done
    • Test motion and shorts '
    • Fiducialize positions (stac5 A1=2/3/4 mm holes, manual A2=4/6/8 mm holes) (S&A) awaiting cubes
  • Prebuncher - high power testing
  • PSS kicker
    • build bids received, choosing one done
    • 12/9: req submitted
  • MagTest
    • Wrapping up A2 measurements
    • Wrapping up A1 measurements


Tunnel work
  • Wien cable pulls (Dela Cruz)
  • Laser alignment work (CIS) complete for this week
  • Gun -> Y-chamber vacuum connections (CIS) Thursday/Friday
  • Viewer cable terminations (Norris)


ISB Work
  • Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos)
  • PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
  • Viewer upgrades, IN03B{06-07} (Norris)
  • Harp upgrades, IN03B07 (Dela Cruz)
  • CIS Rack Work, IN01B{00-05} (Windham)


Injector Tunnel and Service Building

Location
Time
Mon 12/7 Tue 12/8 Wed 12/9 Thu 12/10 Fri 12/11
InjSB
5a - 9a
M Viewer/Wien/Harp Work Viewer/Wien/Harp Work R Viewer Terminations
Tunnel
5a - 9a
CIS Laser Work CIS Laser Work CIS Laser Work S&A+CIS Drive Laser Alignment Locking in NEG-tube
BPM locations (CIS+S&A)
InjSB
9a - 12p
CIS Rack Work CIS Rack Work
Viewer/Wien/Harp Work
CIS Rack Work
Viewer/Wien/Harp Work
CIS Rack Work CIS Rack Work
Viewer Terminations
Wien Cabling Work
Tunnel
9a - 12p
CIS Laser Work CIS Laser Work-
temp Vacuum Window Install
Facilities HVAC Investigation
CIS Laser Work S&A+CIS Drive Laser Alignment CIS Pump Down Gun
S&A Gun/Y-Chamber
InjSB
12p - 4p
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
Viewer Terminations
Wien Cabling Work
Tunnel
12p - 4p
CIS Laser Work CIS Laser Work
Facilities HVAC Investigation
CIS Laser Work S&A+CIS Drive Laser Alignment CIS Pump Down Gun
S&A Gun/Y-Chamber


InjSB Week11.png


Week 13 (Dec 14 - Dec 18)

Non-Tunnel Work
  • Wien (Test Lab)
    • U-Wien electrode parallelism evaluation after assembly w/teflon spacer block, spacer for hangers added (S&A) done
    • Controls work continues yep
    • HV PS calibration measurements, second-pass Friday
    • Receive Nickel endplates? done
  • A1/A2 cubes (Test Lab)
    • Assembling A1/A2 cubes done
    • Test motion and shorts done
    • Fiducialize positions (stac5 A1=2/3/4 mm holes, manual A2=4/6/8 mm holes) (S&A) A2 done, A1 completed today
  • MagTest
    • Measure DR per Jay's plan continues
    • QW (Wien quad) lead reinforcement and field mapping 4 done, 12 to go


Tunnel work
  • Wien cable pulls (Dela Cruz) (latter half of the week) done?
  • Viewer cable terminations? (Norris) near complete
  • Gun -> Y-chamber vacuum pumpdown and leak check (Stutzman, Adderley) done
  • CIS Check drive laser -> cathode -> retroreflection alignment w/assembly under vacuum done
  • SSG Backs out of Laser Bypass workaround in support of PSS upgrades Friday


ISB Work
  • Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz)
  • PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
  • Viewer upgrades, IN03B{06-07} (Norris)
  • Harp upgrades, IN03B07 (Dela Cruz)
  • CIS Rack Work, IN01B{00-05} (Windham)


Injector Tunnel and Service Building

Location
Time
Mon 12/14 Tue 12/15 Wed 12/16 Thu 12/17 Fri 12/18
InjSB
5a - 9a
Viewer Terminations Viewer Terminations W R F
Tunnel
5a - 9a
CIS Vacuum Work:
heating NEG chambers
CIS Vacuum Work:
Leak Checks
Wien HV Cable Pulls? Wien HV Cable Pulls? F
InjSB
9a - 12p
CIS Rack Work
Viewer Terminations
CIS Rack Work
Viewer Terminations
CIS Rack Work CIS Rack Work
PSS Upgrades:
Access Room and in Racks
CIS Rack Work
Tunnel
9a - 12p
CIS Vacuum Work:
heating NEG chambers
CIS Vacuum Work:
Leak Checks
CIS Laser/retroreflection checks
CIS Laser Hut Work
Viewer Terminations
Wien HV Cable Pulls?
CIS Laser Hut Work
Viewer Terminations
SSG Laser Bypass Backout
InjSB
12p - 4p
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrades:
Access Room and in Racks
CIS Rack Work
PSS Upgrade
CIS Rack Work
Tunnel
12p - 4p
CIS Vacuum Work CIS Vacuum Work
CIS Laser/retroreflection checks
CIS Laser Hut Work
Viewer Terminations
CIS Laser Hut Work
Viewer Terminations
F


InjSB Week11.png

Week 13.6 (Dec 21 - Dec 23)

830 toolbox meetings suspended.
Have a safe and restful winter break.

Non-Tunnel Work

MagTest --

  • DR field mapping continues


Tunnel work
  • Neutron detector field cable runs, above 0L03 (Gonzales)
  • PSS upgrades -- equipment near Inj-NL gate (SSG)


ISB Work
  • CIS Rack Work, IN01B{00-05} (Windham)
  • Viewer terminations, IN03B{06, 07} (Norris)
  • PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere (SSG)
  • Neutron detector system work, IN03+4 (Gonzales, Mock)


InjSB Week13.5.png


Week 14 (Jan 4 - Jan 8)

Happy New Year!!! πŸŽ‰πŸŽ‰πŸŽ‰

  • AIPINJ Phase I Jobs for 2021


Non-Tunnel Work
  • Wien
    • V-Wien (Hernandez-Garcia)
      • remove from UITF test stand
      • re-assemble in Vertical orientation w/new spacers, Ni endplates, and magnet
      • ~Wed deliver to S&A
      • Survey of V-wien, evaluation of electrode parallelism
    • Picking up new Ni endplates from machine shop, cleaning and annealing before delivery to MagTest to be used in assembly of H-wien and evaluation during field mapping (Grames)
    • Fabrication of HV switcher chassis continues (Dela Cruz)
    • Controls work continues (Croke)
  • A1/A2 Apertures
    • Motor controls work continues (Windham)
    • A1/A2 girder build in TL continues (Adderley)
  • MagTest
    • DR field mapping
    • Complete QW coils lead reinforcement and mapping
    • Begin H-wien field mapping?


Tunnel work
  • Prepping for Gun2 bake (Stutzman)
  • Wien HV cable pulls? (Dela Cruz, Norris)
  • Laser hut opto-mechanical work (Zhang)
  • LCW walkthrough (CIS+I&C+MechInstall)


ISB Work
  • Wien HV cable pulls?, IN01B{00+01} (Dela Cruz, Norris)
  • PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
  • CIS Rack Work, IN01B{00-05} (Windham)
  • Viewer upgrades, IN03B{06+07} (Norris)
  • 15deg dipole interlock panel install, IN01B11 (Windham)
  • iocin3 crate upgrade to VME, IN01B{04+14} (Dela Cruz)


Injector Tunnel and Service Building

Location
Time
Mon 1/4 Tue 1/5 Wed 1/6 Thu 1/7 Fri 1/8
InjSB
5a - 9a
M T W R F
Tunnel
5a - 9a
M Wien HV cable pulls? MechInstall Crane Work
Wien HV cable pulls?
Viewer Terminations
Wien HV cable pulls?
Viewer Terminations
Wien HV cable pulls?
Viewer Terminations
InjSB
9a - 12p
CIS Rack Work CIS Rack Work --
15deg Interlocks Panel
CIS Rack Work
iocin3 crate upgrade prep
15deg Interlocks Panel CIS Rack Work
Tunnel
9a - 12p
Gun2 Bake Preps 9a LCW Manifold WalkThru
Gun2 Bake Preps
Viewer Terminations
Gun2 Bake Preps
Viewer Terminations
Gun2 Bake Preps
Viewer Terminations
Gun2 Bake Preps
Viewer Terminations
InjSB
12p - 4p
CIS Rack Work
PSS Upgrades
CIS Rack Work --
15deg Interlocks Panel
PSS Upgrades
CIS Rack Work
iocin3 crate upgrade prep
PSS Upgrades
15deg Interlocks Panel
PSS Upgrades
CIS Rack Work
PSS Upgrades
Tunnel
12p - 4p
Gun2 Bake Preps Gun2 Bake Preps Gun2 Bake Preps Gun2 Bake Preps Gun2 Bake Preps


InjSB Week14.png

Week 15 (Jan 11 - Jan 15)

Non-Tunnel Work
  • Wien (Hernandez-Garcia)
    • Bake V-wien
    • V-wien HV soak
    • Fabrication of HV switcher chassis (Dela Cruz)
  • A1/A2 girder build (Adderley)
  • Rectify viewer air cylinder lengths? (Stutzman)
  • MagTest
    • DR field mapping
    • Complete QW coils lead reinforcement and mapping
    • Begin H-wien field mapping?


Tunnel work
  • Photocathode suitcase bake (Stutzman, Adderley)
  • Wien HV cable pulls? (Dela Cruz, Norris)
  • Laser hut work (Zhang)
  • iocin3 job Tuesday
Gun HV control => no problem
Some vacuum => no problem
Some FSD => no problem
Insertables (viewers etc.) => no problem
Some Pockels cell & RTP cell controls => i turned off RTP HV PS already
Chopping aperture (not sure how current this is) => no problem
Scraper (think this is redundant?) => do we remove now???
Maybe some old laser controls (ocelot?) => is this really a running app???
An application called pol_source, which has controls for a number of boards - IP Digital 24, BASIC stepper motor, IpOpto. => => what is this connected to???
Are the remaining 4-laser apps on iocin3b? Will that mini-crate be replaced or merged? Any other apps on iocin3?


ISB Work
  • ⚑⚑⚑Power Outage⚑⚑⚑ I-BT Breaker Panel Work -- adding 50A circuit for new chopper SSA along with 225A main breaker
    Details of what will lose power in ATLis 21696, Tunnel and SB racks affected
  • PSS Upgrades -- energizing new equipment, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
  • CIS Rack Work, IN01B{00-05} (Windham)
  • Viewer upgrades, IN03B{06+07} (Norris)
  • 15deg dipole interlock panel install, IN01B11 (Windham)
  • iocin3 crate upgrade to VME, IN01B{04 + 14} (Dela Cruz)
    • iocin3 will be down Monday 1/11 morning


Injector Tunnel and Service Building

Location
Time
Mon 1/11 Tue 1/12 Wed 1/13 Thu 1/14 Fri 1/15
InjSB
All Day
Safing out equipment for iocin3 work T W Breaker Panel Work Float for breaker panel work
InjSB
Morning
M iocin3 VME upgrade
15deg interlock work
W Breaker Panel Work F
InjSB
Afternoon
PSS Upgrades 15deg interlock work
PSS Upgrades
PSS Upgrades Breaker Panel Work
PSS Upgrades
PSS Upgrades
Tunnel
All Day
Suitcase bake
Safing out equipment for iocin3 work
Suitcase bake W Breaker Panel Work Float for breaker panel work
Tunnel
Morning
M T W Breaker Panel Work F
Tunnel
Afternoon
M T W Breaker Panel Work F

InjSB Week14.png


Week 16 (Jan 18 - Jan 22 +weekend)

Non-Tunnel Work
  • Wien (Hernandez-Garcia)
    • Moving V-wien from UITF test stand to vacuum lab, w/local vac PS Leaving on test stand until need to move
    • H-Wien
      • Preparing to receive Wed 1/20 Fri 1/22
      • Assemble with Ni end plates
      • UHV cleaning
  • A1/A2 girder build (Adderley, Stutzman)
    • Rectifying viewer air cylinder dimensions
  • Prebuncher testing/tuning (Wissman)
  • MagTest
    • H-wien field mapping (ETA Fri 1/22)
    • DR#2 coil lead reinforcement
    • DR#1 upper coil inspection


Tunnel work
  • Fire pipe install, pipe delivery 1/22, install begins Saturday 1/23
  • Wien HV cable pulls? (Dela Cruz, Norris)
  • Laser hut work (Zhang)
  • Vacuum bakes (Stutzman, Adderley)
  • FC#1 bellows replacement (Adderley, Stutzman, Grames)


ISB Work
  • PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
  • CIS Rack Work, IN01B{00-05} (Windham)
  • Viewer upgrades, IN03B{06+07} (Norris)
  • 15deg dipole interlock panel install, IN01B11 (Windham)
  • Chopper SSA upgrade, back of IN01B{10-15} (Farrish)


Injector Tunnel and Service Building

Location
Time
Mon 1/18
MLK Jr Day
Tue 1/19 Wed 1/20 Thu 1/21 Fri 1/22 Weekend
Sa 23rd + Su 24th
InjSB
All Day
holiday CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work weekend
InjSB
Morning
M Beam Sync Cabling
Check (~IN01B04) Francis
15deg Interlock
Chopper SSA Cabling
W CIS Rack Work CIS Rack Work weekend
InjSB
Afternoon
M 15deg Interlock
PSS Upgrades
Laser chiller checkout
PSS Upgrades
CIS Rack Work
PSS Upgrades
CIS Rack Work
PSS Upgrades
weekend
Tunnel
All Day
holiday Laser Hut Work
Vacuum Bakes
FC#1 Bellows Replacement R Fire pipe install Fire pipe install
Tunnel
Morning
M T W FC#1 Vacuum Button-Up
Viewer Terminations
Fire pipe install Fire pipe install
Tunnel
Afternoon
M T Laser Hut Work FC#1 Vacuum Button-Up
Laser Hut Work
Fire pipe install Fire pipe install


InjSB Week16.png

Week 17 (Jan 25 - Jan 29)

Non-Tunnel Work
  • Wien (Hernandez-Garcia)
    • H-Wien
      • Receive from MagTest after field mapping
      • Assemble with Ni end plates
      • UHV cleaning
    • U-Wien newly fabricated Ni endplates
      • Pick-up after ultrasonic isopropanol clean 1/25
      • Deliver for annealing
    • V-Wien
      • Remove from UITF cave and begin assembling on girder?
  • A1/A2 girder build (Adderley, Stutzman)
  • Rectifying viewer air cylinder dimensions (Adderley, Machie, Gregory)
  • Prebuncher testing/tuning (Wissman)
  • Survey and Alignment
    • PCup survey and fiducialization
    • FC#1 survey and fiducialization
    • H-wien after UHV cleaning and assembly using teflon spacer method
    • Individual H-wien electrodes, and U-wien ones for comparison
  • MagTest
    • QW coil thermal tests
    • QW coil quality control checks


Tunnel work
  • Fire pipe (FML subcontractor)
    • Install
    • Pressurized air test
    • Pressurized water test (hydrotest)
  • Laser hut work (Zhang)
  • Preps for prep-chamber and HV chamber bakes next week (Stutzman, Adderley)
  • 120V front-end outlets walkthru (Windham, Stutzman, Adderley, Grames)
  • Cryo relief valve PM, behind 0L02 (Cryo)
  • Stowing photocathodes in suitcase for bakes (Grames)
  • Gate valve controller checkout/documentation (Windham)


ISB Work
  • PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
  • CIS Rack Work, IN01B{00-05} (Windham)
  • Viewer upgrades, IN03B{06+07} (Norris)
  • 15deg dipole interlock panel, IN01B11 (Windham)
  • Utility chassis swaps, IN02B{10,11,26} + IN04B10 (Diggs, Kissinger)


Injector Tunnel and Service Building

Location
Time
Mon 1/25 Tue 1/26 Wed 1/27 Thu 1/28 Fri 1/29
InjSB
All Day
M Fire pipe install W Utility chassis swaps F
InjSB
Morning
M Fire pipe install W Utility chassis swaps F
InjSB
Afternoon
PSS Upgrades Fire pipe install
PSS Upgrades
PSS Upgrades Utility chassis swaps
PSS Upgrades
PSS Upgrades
Tunnel
All Day
Fire pipe install Fire pipe install Fire pipe install Cryo relief valve PM Fire pipe hydrotest
Tunnel
Morning
Fire pipe install Fire pipe install Fire pipe install 120V outlets walkthru
Fire pipe air test
Fire pipe hydrotest
Valve controller
Tunnel
Afternoon
Fire pipe install Fire pipe install Fire pipe install
Laser Hut Work
Laser Hut Work Preps for bakes?
Photocathodes->Suitcase?
Laser Hut Work


InjSB Week17.png


Week 18 (Feb 1 - Feb 5)

Non-Tunnel Work
  • Wien (Hernandez-Garcia)
    • H-Wien
      • MS fabricating new frame x4 and
        new 14mm-spacing teflon spacers for electrode assembly
      • Once MS done, towards end of the week, assemble H-wien w/new frame
      • Assembled H-wien -> S&A
    • HV Switcher Chassis (Dela Cruz)
      • 1st chassis hi-potted good
      • 2nd chassis getting overload faults, investigating
  • Viewer assembly (Adderley, Stutzman)
  • Wien girder assembly (Adderley, Stutzman)
    • Wien quads on crosses -- ETA T/W for QW coils from MagTest
  • Add pumps, vacuum leak check A1/A2 girder after S&A (Stutzman, Adderley)
  • Laser box build (Zhang, Gregory)
  • Build spare valve override blackbox, fourth in total (Windham)
  • Survey and Alignment
    • A1/A2 girder 1A pre-alignment
    • H-wien assembled on new frame
  • MagTest
    • Finish QC of QW coils -- Tuesday/Wednesday ETA
    • Thermal and current-limit tests on assembled spare QW-quad
    • Field mapping assembled spare QW-quad


Tunnel work
  • Laser hut work (Zhang)
  • Viewer upgrades (Norris)
  • Prep chamber bake forgoing for now, vacuum sufficiently good
    • Setup (in no particular order)
      • photocathodes->suitcase;
      • breakdown unistrut,
      • stow protective plastic barrier;
      • Configure IPs and valves
    • Bake for ~3 days @ πŸ”₯πŸ”₯πŸ”₯C
    • Breakdown ~Friday
  • Opportunistic preps for HV chamber bake
  • 120V front-end outlets walkthru (Windham, Stutzman, Adderley, Grames)
  • Laser box enclosure design walkthru (Zhang, Gregory)
  • N2 manifold temporary move (Bullard)


ISB Work
  • PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
  • CIS Rack Work, IN01B{00-05} (Windham)
  • Viewer upgrades, IN03B{06+07} (Norris)
  • 15deg dipole interlock panel, IN01B11 (Windham)
  • Install Wien HV Polarity Switcher Chassis, IN01B0{0,1} (Dela Cruz)
Other Service Buildings
  • Prebuncher testing/tuning in BSY SB (Wissman)


Injector Tunnel and Service Building

Location
Time
Mon 2/1 Tue 2/2 Wed 2/3 Thu 2/4 Fri 2/5
InjSB
All Day
CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work
InjSB
Morning
M 15deg dipole intlk tests
Viewer upgrades
15deg dipole intlk tests
Viewer upgrades
R Viewer Upgrades
InjSB
Afternoon
PSS Upgrades 15deg dipole intlk tests
PSS Upgrades
PSS Upgrades 15deg dipole intlk tests
PSS Upgrades
PSS Upgrades
Tunnel
All Day
Prep for Prep Chamber Bake Prep chamber bake
Preps for HV Chamber Bake
Prep Chamber Bake
Preps for HV Chamber Bake
Prep Chamber Bake
Preps for HV Chamber Bake
Prep Chamber Bake Takedown
Preps for HV Chamber Bake
Tunnel
Morning
Valve controller Prep chamber vacuum tests/eval Viewer Upgrades
Engaging Prep RGA
N2 manifold move?
N2 manifold move
Laser enclosure walkthru
Viewer Upgrades
Tunnel
Afternoon
Photocathodes->Suitcase
Valve controller
Laser hut work Laser enclosure walkthru
Laser hut work
Laser hut work Laser hut work


InjSB Week18.png


Week 19 (Feb 8 - Feb 12)

Non-Tunnel Work
  • A1/A2 Girder (Adderley, Stutzman)
    • Prep for install in tunnel
  • Wien (Hernandez-Garcia)
    • H-wien HV testing


Tunnel work
  • A1/A2 girder install (Mech Install)
  • A1/A2 S&A
  • FC#1 Re-install (CIS)
  • FC#1 S&A
  • HV Chamber Bake? (CIS)
  • Laser hut work (Zhang)
  • MDR1I01 Connections (Coleman, DC Power)


ISB Work
  • PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
  • CIS Rack Work, IN01B{00-05} (Windham)
  • Viewer upgrades, IN03B{06+07} (Norris)
  • 15deg dipole interlock panel, IN01B11 (Windham)
  • Install Wien HV Polarity Switcher Chassis, IN01B0{0,1} (Dela Cruz)
  • DC Power connections for 15deg dipole MDR1I02, IN02B22 (Coleman, DC Power)

Injector Tunnel and Service Building

Location
Time
Mon 2/8 Tue 2/9 Wed 2/10 Thu 2/11 Fri 2/12
InjSB
All Day
MDR1I02 Connections MDR1I02 Connections MDR1I02 Connections MDR1I02 Connections MDR1I02 Connections
InjSB
Morning
M T W R F
InjSB
Afternoon
PSS Upgrades PSS Upgrades PSS Upgrades PSS Upgrades PSS Upgrades
Tunnel
All Day
M A1/A2 Girder Install S&A of A1/A2 Girder + FC#1 S&A of A1/A2 Girder + FC#1 F(loat)
Tunnel
Morning
M A1/A2 Girder Install W Re-Install FC#1 F
Tunnel
Afternoon
M T W R F


InjSB Week18.png


Week 20 (Feb 15 - Feb 19)

Non-Tunnel Work
Tunnel work
ISB Work


Injector Tunnel and Service Building

Location
Time
Mon 2/15 Tue 2/16 Wed 2/17 Thu 2/18 Fri 2/19
InjSB
All Day
M T W R F
InjSB
Morning
M T W R F
InjSB
Afternoon
PSS Upgrades PSS Upgrades PSS Upgrades PSS Upgrades PSS Upgrades
Tunnel
All Day
M T W R F
Tunnel
Morning
M T W R F
Tunnel
Afternoon
M T W R F


InjSB Week20.png


Week 21 (Feb 22 - Feb 26)

Non-Tunnel Work
Tunnel work
ISB Work


Injector Tunnel and Service Building

Location
Time
Mon 2/22 Tue 2/23 Wed 2/24 Thu 2/25 Fri 2/26
InjSB
All Day
M T W R F
InjSB
Morning
M T W R F
InjSB
Afternoon
PSS Upgrades PSS Upgrades PSS Upgrades PSS Upgrades PSS Upgrades
Tunnel
All Day
M T W R F
Tunnel
Morning
M T W R F
Tunnel
Afternoon
M T W R F


InjSB Week21.png


Week 22 (Mar 1- Mar 5)

Non-Tunnel Work
Tunnel work
ISB Work


Injector Tunnel and Service Building

Location
Time
Mon 3/1 Tue 3/2 Wed 3/3 Thu 3/4 Fri 3/5
InjSB
All Day
M T W R F
InjSB
Morning
M T W R F
InjSB
Afternoon
PSS Upgrades PSS Upgrades PSS Upgrades PSS Upgrades PSS Upgrades
Tunnel
All Day
M T W R F
Tunnel
Morning
M T W R F
Tunnel
Afternoon
M T W R F


InjSB Week22.png


Penetration Work

InjSB Penetrations that are open (click for pictures): above laser hut, 58, 86, 108, 135

  • 34ft from floor of InjSB to floor of Inj tunnel
  • 25ft from floor of InjSB to elevated Inj tunnel cable tray

Penetration Cable Pulls/Removals --

  • Tony pulling new Wien E-field HV cables
  • Norris removing old Cat5 viewer cables
  • Norris pulling new viewer cables
  • Riad/Scott removing old Mott HV cables
  • Coleman pulling new Wien B-field magnet cables
  • Cole pulling new neutron detector cables (above 0L03)
  • Scott pulling motor control cables for A1++

InjSB Racks.png

Fire System Work

Description of Task: Replacement of tunnel sprinkler piping, fire alarm control panels in B85 & B98, replacement of detection devices.

update 11/9: 25% of demo completed
update 11/23: demo completed
update 12/8: fire pipe installation in Injector slated for Winter break ~12/21 - 1/3
"The drawings needed prior to fabrication of the INJ fire pipe have not gone through the system." No fire pipe install work over winter break.
update 1/7/21: Tentative fire pipe install to occur week of 1/18 in tunnel. Should take 3-4 days, so with the holiday on Monday, likely the rest of the week.
Further fire pipe work upstairs in the service will also need 3-4 days, but won't be constant (i.e. contractor will be in and out).
update 1/18/21: New pipe arriving Fri 1/22. No install work week of 1/18.
update 1/20/21: fire pipe installation to begin 1/22 and continue over weekend 1/23+24.
update 2/1/21: fire pipe installation, air pressure and hydro tests complete.