Phase 1 - HCO & Commissioning
Jump to navigation
Jump to search
Jobs Leading to HCO & Commissioning
- 15 deg dipole (MDR)
- Install on beam line after bake out, then align, do we use shims?
- Current sensor for HV interlock installed and tested, ready for DC power, to set limits, fault test
- Current sensor for FSD installed and tested, calibrated for FSD card, ready for DC power, to set limits, fault test
- Update drawings and documentation
- Laser jobs
- Complete outrigger box, install, test with laser room shutter, update LSOP
- Flush chiller, decide on PM schedule, fill
- Re-install Hall B amp in permanent location
- Complete macropulse chassis upgrade (replace 18 VDC + booster with 24 VDC, add protection diode to shutters), test all beam modes
- Wien HVPS
- (done) Add placards to ISB racks
- Install HV Switcher chassis at ISB, complete cabling between rack components
- Drop/pull HV cables from HV switcher outputs to Wiens
- Ion Pump Power Supplies
- (done) Finalize IP names for songsheet
- Complete mapping between all IP and power supplies (gun to choppers)
- Complete UHV power supply upgrade, remove temp PS, spare PS on shelf (identify cabinet area for spares)
- Work with software to reprogram UHV PS EPICS names, can we have unique identifier from old names?
- Re-install (2) HV patch boxes, update box labels, pull HV drop cables to patch boxes, updated labels
- Valves
- Controls for (3) gate valves
- Air, GN2, LCW
- Move GN2 near gun lower, hook for air lines, caps for poly hose
- Add 2nd GN2 near girder, hook for air lines, caps for poly hose
- Fabricate, install air manifold for viewers and valves
- (done) Re-install LCW manifold
- Electrician jobs
- Relocate floor outlets
- Bond girders (Shaun has holes drilled on girders already for this)
- Install cable tray