2021-04-28
Meeting Information
Connecting
To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/946721076.
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 946721076.
- To join via phone, use one of the following numbers and the Conference ID: 946721076.
- Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Agenda
Schedule
Rough timetable:
- CMTF tests with C75-1 (late-March - early-June).
- UITF beamline Modification in parallel to install new beamline
- Supplementary Shielding Installation: Mid-June
- Beamline Commissioning / Test Plans / Shielding Verification
- 7/26/21 Start Hot Check-out
- Commission new beam line and execute experiment [May slide a week... and weekends also available if desired]
Long Term Schedule (McCaughan) Strawman
New items for discussion:
- Beam Studies updates
- Short term schedule update:
- This week:
- Component disconnects (Mostly complete)
- Stage larger table for beamline prep behind MeV dump (Complete)
- Vent elevated line for component removal (Complete)
- Pull components from elevated line (In progress)
- Diagnose Chopper slit (Complete - gear box issue; on A5 controls/STAC5 now. Thanks to Scott!)
- Build 80/20 support structure; add mounting plates/brackets/etc. (Complete under solenoid; Pb table still needs construction)
- Gun work (Alignment work in progress...)
- Target interlock completed for beam mode with SCAM (Thanks to all involved!)
- Shaun iterating on design to add additional viewer per Yan/Matt's request
- Pull Heliax from Sprectrum analyzer/Control room >> Buncher
- Ready to install Al base plates for FC3 region rework as well as solenoid stand
- Inventory Faye's old office for materials
- Vacuum work / Beam line assembly Fridays starting at 9am for any who want to participate
- Next Week:
- Unistrut mounting for cables / gas bottle rack
- Post 2-d schematic for install
- Install the brackets and flange supports
- PEPPo magnet/Solenoid
- Gasket purchase: Dunniway Stock Room or Kurt Lesker (silver plated, 2.75", 4.5" and 4 5/8", 30 ea. plus blank 2.75" for the conductance limiting aperture, pack of 10) - Copy from Matt/Marcy's req queue.
- Do we have fluorescing screen on hand for behind samples?
- Parts for install; give them to Teena for UHV cleaning...
- This week:
- Engineering
- Other business
Reports on Open Action Items:
- Action Items:
- Formal run plan