CIS Phase 1 work plans

From Ciswikidb
Jump to navigation Jump to search

2020 Weeks 1 through 13

Week 14 (Jan 4 - Jan 8)

Week 15 (Jan 11 - Jan 15)

Week 16 (Jan 18 - Jan 22 +weekend)

Week 17 (Jan 25 - Jan 29)

Week 18 (Feb 1 - Feb 5)

Week 19 (Feb 8 - Feb 12)

Week 20 (Feb 15 - Feb 19)

Week 21 (Feb 22 - Feb 26)

Week 22 (Mar 1- Mar 5)

Week 23 (Mar 8 - Mar 12)

Week 24 (Mar 15 - Mar 19)

Week 25 (Mar 22 - Mar 26)

Week 26 (Mar 29 - Apr 2)

Week 27 (Apr 5 - Apr 9)

Week 28 (Apr 12 - Apr 16)

Week 29 (Apr 19 - Apr 23)

Week 30 (Apr 26 - Apr 30)

Week 31 (May 3 - May 7)

Week 32 (May 10 - May 14)

Week 33 (May 17 - May 21)

Collapse
Tunnel work
  • Finish HCO ====> Beam Commissioning!
    • First CEBAF beam of 2021
    • First ~4m of Injector newly upgraded


  • Equipment crane-out (MechInstall)
  • Viewer HCO (Norris)
  • Harp 0I02 electronics install and HCO (Dela Cruz)
  • Magnet HCO (Coleman)
  • CIS HCO
    • Laser alignment optimization (Zhang)
    • 1/2 Waveplate T/S (Windham)
    • Photocathode activation (Grames)
    • Wien system HCO (Hernandez-Garcia, Dela Cruz)
    • Ion pump noise investigation (Stutzman)


  • 60Hz electrical noise snooping (Suleiman) evenings


ISB Work
  • CIS Rack Work, IN01* (Windham)
  • Wien System HCO, IN01B0{0,1} (Dela Cruz, Hernandez-Garcia)
  • ItoV System Checkout, FC2 unlock (Francis) Mon
  • Magnet HCO, IN02B{10,11,26}+IN04B10 (Coleman)
  • Viewer HCO, IN01B04+IN03B0{6,7} (Norris)
  • Harp HCO, IN01B03+IN03B06 (Dela Cruz)


  • VEPCO Automatic Voltage Regulators Test, ATLis 22392
    • Voltage will be adjusted remotely to verify operation of automatic voltage regulators. If there is a huge problem... there could be a power outage.
    • Incoming power voltage variation < +/- 10%
    • "Be prepared for a power interruption"


Injector Tunnel and Service Building

Location
Time
Mon 5/17 Tue 5/18 Wed 5/19 Thu 5/20 Fri 5/21
InjSB
All Day
Service Building Clean-Up
Wrapping up HCO
⚡VEPCO Voltage Tests
1030a-noon (4th attempt?)
InjSB
Early
Morning
<9a
InjSB
Morning
Magnet HCO
InjSB
Afternoon
Magnet HCO
Tunnel
All Day
Wrapping up HCO
Wien HV Soak
PSS Certs
Beam Commissioning
Beam Commissioning
⚡VEPCO Voltage Tests
1030a-noon (4th attempt?)
Beam Commissioning Beam Commissioning
Tunnel
Early
Morning
<9a
0I02 anti-collision (1 ppl)
Tunnel
Morning
Magnet HCO (2-5ppl) 11a: HCO Committee tour (3ppl) 830-9a: Cryo tour (3ppl)
Tunnel
Afternoon
Laser hut work?
Magnet HCO (2-5ppl)
Evening: 60Hz snooping
Lock-up: PSS Certs
Beam Commissioning

Tunnel Personnel Loading Limits: Injector, upstream of plastic curtain, total=8 -> 4 upstream of laser hut, 4 downstream of laser hut

InjSB Week30 1.png

Penetration Work

Fire System Work