Phase 1 Commissioning ATLIS tasks
Jump to navigation
Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
- General / Catch-All Test Plans
- 22060 Beam Commissioning AIPINJ Phase I (general ATLis)
- 21170 Injector Upgrade - Phase 1 Installation (Gun to Chopper)
- With-Beam Hardware Commissioning Test Plans
- 22441 Commissioning V-Wien, H-Wien, Spin Flipper Solenoids and Autosteer Knobs
- 22061 PSS Kicker Tests @ 130keV & 200keV
- 22080 AIPINJ: 130/200 keV HVPS vs. PCUP current monitor calibration
- 22082 AIPINJ: 130/200 keV lifetime measurements
- 22313 Compare Beam Transmission for Gun Biased at 130 and 200kV
- Beam Commissioning
- 22180 Gun to Chopper Commissioning _130keV / 200keV beam to PCup
- 22181 Early Injector Orbit Data Collection Rev. April/May 2021
- 22182 Set up beam from PCup to FC1 at 130keV
- 22183 Beam steer from FC1 to FC2
- 22184 Efficacy of Knobs chosen for spot move correction
- Optics/RF Test Plans
- 21923 Perform 130keV emittance measurements and matching as part of Injector Upgrade commissioning
- 22072 Perform 200keV emittance measurements and matching as part of Injector Upgrade commissioning
- 19784 Test multiwire emittance measurement with beam
- 22160 Measure optics at various coil fixture rotation angles for MDR1I02
- 22190 RF Elements Setup (Injector Upgrade Phase 1), Lasers phases, Prebuncher, and Choppers
- 22250 0I02 Viewer vs Harp Emittance Measurement
- Spin/Wien Test Plans
- 22441 Commissioning V-Wien, H-Wien, Spin Flipper Solenoids and Autosteer Knobs
- 22090 Mott Hot Checkout
- 22091 Spin Dance to Calibrate Upgraded CEBAF Injector 3D Spin Rotator
- 22092 Set 3D Spin Rotator: Flip-Right, Flip-Left, and Vertical Polarizarion
- 22083 AIPINJ: Test new hysteresis function for spin solenoids (MFG1I04A/B)
- 22084 AIPINJ: 130/200 keV E/B calibrations for V-Wien and H-Wien
- 22330 Measuring time of flight to chopper master slit versus Wien spin angle
- Parity Quality Beam Test Plans