6/4/21 - Planning meeting

From Ciswikidb
Revision as of 16:38, 6 June 2021 by Grames (talk | contribs) (Created page with "Summary of conference call... #Eric will work with Dave to seek a JLab solution for fabricating the 125um thin graphite "wedges" #Marcy will work with Danny to select and fin...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Summary of conference call...

  1. Eric will work with Dave to seek a JLab solution for fabricating the 125um thin graphite "wedges"
  2. Marcy will work with Danny to select and finalize two kapton coated K type thermo-couples, attaching to rear of ladder
  3. Eric will ship ladder & one diamond holder assembly to JLab when ready, late June or early July, JLab will clean, assemble ladder, TC, viewer
  4. Scott will instrument the translator motion (once he has the translator!), and work with survey & alignment to calibrate target positions (once assembled!)
  5. Joe will keep everyone posted on schedule, most likely installation window is week of July 12, and opportunistic beam tests July 16 - Aug 26.