June 9, 2021 - Group Meeting
Jump to navigation
Jump to search
- Group business
- new hires
- MEDCON4
- re-"Grouping"
- power outages (CEBAF, TL, UITF, GTS) - media:Building 58 After hour e-call listing June.08.2021 - PJD.docx
- Geoff is inquiring if we want another stream of PhD students
- CEBAF
- Restoration begins July 16 (~5 weeks)
- Commissioning - I don't see how it all fits, restoring CEBAF for the Fall run would be top priority
- Things maybe left to do?
- PCup - water leak and pig-tail?
- Wien HV - work with injector group to decide mode of operation
- Harp - work with ME group to develop a solution, decide if/when to install
- Mode-locked fiber laser
- Mott target ladder swap
- Phase 2 - who thinks we're ready by January?
- UITF
- Restoration begins July 26 (~6 weeks)
- Clean HV chamber
- New cathode and anode spider (~week?)
- Prep chamber - mask, pucks, Sb source
- Bake (~week) + condition (~week)
- GTS
- Re-building depo, gun, beam line, laser, HV controls - wow!
- Once built, program til end of year...
- Students, FOA's, LDRD's, SBIR's ...
- Students - Sajini, Josh
- LDRD's - Shukui, Joe
- Photocathode & HV FOA's
- SBIR's
- Lab projects
- EIC
- ILC