Phase 1 Commissioning Schedule
Week 0, May 17th-23rd
Week 1, May 24th-30th
Week 2, May 31st🇺🇸 - June 6th
Week 3, June 7th-13th
Week 4, June 14th-20th
Week 5, June 21st-27th
Collapse
- SCMB reviewing proposal to run without PSS Kicker for FC2/ILD running (same PSS mode) Monday 6/21
- 500keV-limited (i.e. 1D/FC1) until SCMB approval
Monday Swing, may be able to run to FC2- ILD running contingent on SCMB approval and HCO completion
- SCMB Update 6/22 -- No FC2 running just yet. Current forecast, Friday Swing
OWL Shift | Monday 6/21 |
Tuesday 6/22 |
Wednesday 6/23 |
Thursday 6/24 |
Friday 6/25 |
Saturday 6/26 |
Sunday 6/27 |
Notes/Goals |
---|---|---|---|---|---|---|---|---|
Beam Commissioning Plan (ATLis) |
AutoSteer Knobs (22441) | 8P-4A : AutoSteer (22441) 6A-11A: Adviewer 0I02 YAG Emittance Measurement Tool Development (22603) |
midnight - 6A: AutoSteer 6A: Open for HCO |
FC2 Setup (22183) | FC2 Setup (22183) | FC1/1D/500keV limited on weekday Day shifts -- NL Open for Work | ||
Shift Leader | Law | 8P-4A: Law 6A-11A: Freeman |
Law | Law | Law | |||
Scientist #2 | ||||||||
Crew Chief | Forman | Forman | Forman | Forman | Forman | Law | Law | |
SSO | Garcia | Garcia | Garcia | Garcia | Garcia | Garcia | Garcia | |
DAY Shift | 6/21 | 6/22 | 6/23 | 6/24 | 6/25 | 6/26 | 6/27 | |
Beam Commissioning Plan (ATLis) |
Perform 130keV emittance measurements (21923) (using 0I02 YAG) |
ToF vs HWien Angle (22330) | 6A-11A: Adviewer 0I02 YAG Emittance Measurement Tool Development (22603) noon-4P: Wien orbit checks, HV offset measurement |
Open, No Beam, Till ~(10A-noon) noon - 4P: 2I Steering Investigation |
8A-noon: rotatable 1/2 waveplate scans and BPM sensitivity (22120) noon - 4P: injSteeringScript |
FC2 Setup (22183) | TBD | |
Shift Leader | Turner | Poelker | 6A-11A: Freeman noon-4P : Suleiman |
Bruker | 8A-noon: Amali noon - 4P: Hofler |
Wang | TBD | |
Scientist #2 | Mamun | Bruker | Bruker | 8A-noon: Grames noon-4P: Joyce |
||||
Crew Chief | Aiken | Aiken | Aiken | Aiken | Aiken | Freeman | Freeman | |
SSO | Gauthier | Frierson | Frierson | Gauthier | Gauthier | Jones | Jones | |
SWING Shift | 6/21 | 6/22 | 6/23 | 6/24 | 6/25 | 6/26 | 6/27 | |
Beam Commissioning Plan (ATLis) |
H-Wien Orbit Deflection Studies | Continuation of ToF Studies 8P-4A : AutoSteer (22441) |
Physics Run Wien Setup w/ High Current/Transmission (22182) | PSS Functional Tests No Beam After: Physics Run Wien Setup |
FC2 Setup (22183) | FC2 Setup (22183) | TBD | |
Shift Leader | Bruker | Grames 8P-4A: Law |
Wang | Wang | Kazimi | Hofler | TBD | |
Scientist #2 | Hofler | Kazimi | ||||||
Crew Chief | Moser | Moser | Moser | McCaughan | McCaughan | McCaughan | McCaughan | |
SSO | Anthony | Anthony | Anthony | Anthony | Anthony | Mock | Mock |
Week 6, June 28th-July 4th
Collapse
OWL Shift | Monday 6/28 |
Tuesday 6/29 |
Wednesday 6/30 |
Thursday 7/1 |
Friday 7/2 |
Saturday 7/3 |
Sunday 7/4 🇺🇸 |
Notes/Goals |
---|---|---|---|---|---|---|---|---|
Beam Commissioning Plan (ATLis) |
TBD | TBD | TBD | TBD | TBD | TBD | TBD | ILD running possible once HCO complete and BA granted |
Shift Leader | ||||||||
Scientist #2 | ||||||||
Crew Chief | Law | Law | Law | Law | Forman | Forman | Forman | |
SSO | Deir | Deir | Deir | Deir | Deir | Garcia | Garcia | |
DAY Shift | 6/28 | 6/29 | 6/30 | 7/1 | 7/2 | 7/3 | 7/4 🇺🇸 | |
Beam Commissioning Plan (ATLis) |
TBD | TBD | TBD | TBD | TBD | TBD | TBD | |
Shift Leader | ||||||||
Scientist #2 | ||||||||
Crew Chief | Aiken | Aiken | Freeman | Frierson | Merz | Merz | Merz | |
SSO | Gauthier | Gauthier | Gauthier | Jones | Jones | Aiken | Aiken | |
SWING Shift | 6/28 | 6/29 | 6/30 | 7/1 | 7/2 | 7/3 | 7/4 🇺🇸 | |
Beam Commissioning Plan (ATLis) |
TBD | TBD | TBD | TBD | TBD | TBD | TBD | |
Shift Leader | ||||||||
Scientist #2 | ||||||||
Crew Chief | McCaughan | McCaughan | Moser | Moser | Moser | Carlino | McCaughan | |
SSO | Mock | Mock | Mock | Mock | Mock | Anthony | Anthony |
Week 7, July 5th-July 11th
Week 8, July 12th-July 16th