Phase 1 Commissioning Schedule

From Ciswikidb
Revision as of 20:20, 27 June 2021 by Bruker (talk | contribs)
Jump to navigation Jump to search

Week 0, May 17th-23rd

Week 1, May 24th-30th

Week 2, May 31st🇺🇸 - June 6th

Week 3, June 7th-13th

Week 4, June 14th-20th

Week 5, June 21st-27th

Collapse
  • SCMB reviewing proposal to run without PSS Kicker for FC2/ILD running (same PSS mode) Monday 6/21
    • 500keV-limited (i.e. 1D/FC1) until SCMB approval
    • Monday Swing, may be able to run to FC2
    • ILD running contingent on SCMB approval and HCO completion
  • SCMB Update 6/22 -- No FC2 running just yet. Current forecast, Friday Swing
  • Update 6/25 -- TOSP signed, BA to FC2 approved. BA to ILD pending (HCO incomplete).
OWL Shift Monday
6/21
Tuesday
6/22
Wednesday
6/23
Thursday
6/24
Friday
6/25
Saturday
6/26
Sunday
6/27
Notes/Goals
Beam Commissioning
Plan (ATLis)
AutoSteer Knobs (22441) 8P-4A : AutoSteer (22441)
6A-11A: Adviewer 0I02 YAG Emittance Measurement Tool Development (22603)
midnight - 6A: AutoSteer
6A: Open for HCO
FC2 Setup (22183) Setup 90° HWien for Mott measurement FC1/1D/500keV

limited on
weekday Day
shifts -- NL
Open for Work
Shift Leader Law 8P-4A: Law
6A-11A: Freeman
Law Law Law
Scientist #2
Crew Chief Forman Forman Forman Forman Forman Law Law
SSO Garcia Garcia Garcia Garcia Garcia Garcia Garcia
DAY Shift 6/21 6/22 6/23 6/24 6/25 6/26 6/27
Beam Commissioning
Plan (ATLis)
Perform 130keV emittance measurements (21923)
(using 0I02 YAG)
ToF vs HWien Angle (22330) 6A-11A: Adviewer 0I02 YAG Emittance Measurement Tool Development (22603)
noon-4P: Wien orbit checks, HV offset measurement
Open, No Beam, Till ~(10A-noon)
noon - 4P: 2I Steering
Investigation
8A-noon: rotatable 1/2 waveplate scans and BPM sensitivity (22120)
30 uA to FC1

noon - 4P: injSteeringScript
FC2 Setup (22183) Mott
Shift Leader Turner Poelker 6A-11A: Freeman
noon-4P : Suleiman
Bruker 8A-noon: Amali
noon - 4P: Hofler
Wang Suleiman
Scientist #2 Mamun Bruker Bruker Hofler 8A-noon: Grames
noon-4P: Joyce
Bruker
Crew Chief Aiken Aiken Aiken Aiken Aiken Freeman Freeman
SSO Gauthier Frierson Frierson Gauthier Gauthier Jones Jones
SWING Shift 6/21 6/22 6/23 6/24 6/25 6/26 6/27
Beam Commissioning
Plan (ATLis)
H-Wien Orbit Deflection Studies Continuation of ToF Studies
8P-4A : AutoSteer (22441)
Physics Run Wien Setup w/ High Current/Transmission (22182) PSS Functional Tests
No Beam

After: Physics Run Wien Setup
FC2 Setup (22183) FC2 Setup (22183) 0L orbit checks; 0L03 harp emittance measurement
Shift Leader Bruker Grames
8P-4A: Law
Wang Wang Kazimi Hofler Bruker
Scientist #2 Hofler, Bruker Kazimi
Crew Chief Moser Moser Moser McCaughan McCaughan McCaughan McCaughan
SSO Anthony Anthony Anthony Anthony Anthony Mock Mock

Week 6, June 28th-July 4th

Collapse

Yan: tentatively available every day, DAY or SWING as needed.
Joe: available to heat/reactivate the cathode as necessary.

OWL Shift Monday
6/28
Tuesday
6/29
Wednesday
6/30
Thursday
7/1
Friday
7/2
Saturday
7/3
Sunday
7/4 🇺🇸
Notes/Goals
Beam Commissioning
Plan (ATLis)
Continue 90° HWien w/ good transmission and auto-steer Mott TBD TBD TBD TBD TBD ILD running
possible
once HCO
complete and
BA granted
Shift Leader Law Suleiman
Scientist #2
Crew Chief Law Law Law Law Forman Forman Forman
SSO Deir Deir Deir Deir Deir Garcia Garcia
DAY Shift 6/28 6/29 6/30 7/1 7/2 7/3 7/4 🇺🇸
Beam Commissioning
Plan (ATLis)
morning TBD; 12-24 Bunch length system check and measurement Heat and activate cathode TBD TBD TBD TBD TBD
Shift Leader morning TBD; 12-24 Kazimi Grames
Scientist #2 12-24 Hofler; 12-16 Bruker
Crew Chief Aiken Aiken Freeman Frierson Merz Merz Merz
SSO Gauthier Gauthier Gauthier Jones Jones Aiken Aiken
SWING Shift 6/28 6/29 6/30 7/1 7/2 7/3 7/4 🇺🇸
Beam Commissioning
Plan (ATLis)
12-24 Bunch length system check and measurement Heat and activate cathode (cont'd), no beam TBD TBD TBD TBD TBD
Shift Leader 12-24 Kazimi Grames
Scientist #2 12-24 Hofler
Crew Chief McCaughan McCaughan Moser Moser Moser Carlino Carlino
SSO Mock Mock Mock Mock Mock Anthony Anthony

Week 7, July 5th-July 11th

Week 8, July 12th-July 18th

High-Level View June 7th-July16th