Phase 1 Commissioning Schedule
Week 0, May 17th-23rd
Week 1, May 24th-30th
Week 2, May 31st🇺🇸 - June 6th
Week 3, June 7th-13th
Week 4, June 14th-20th
Week 5, June 21st-27th
Week 6, June 28th-July 4th
Collapse
Yan: tentatively available every day, DAY or SWING as needed.
Update 6/29: ILD HCO pending; sending beam there not expected until 7/9. However, the main machine is facing delays as well. There is understandable reluctance about staffing the MCC during the weekend (including Monday, observing 👽) if supporting the injector tasks is unnecessary in terms of being on time overall. We are therefore trying not to schedule anything for the weekend at this time.
OWL Shift | Monday 6/28 |
Tuesday 6/29 |
Wednesday 6/30 |
Thursday 7/1 |
Friday 7/2 |
Saturday 7/3 |
Sunday 7/4 🇺🇸 |
Notes/Goals |
---|---|---|---|---|---|---|---|---|
Beam Commissioning Plan (ATLis) |
Continue 90° HWien w/ good transmission and auto-steer | Mott | Spot move and Wien setup for Mott measurement | Wien setup | FC2 Setup (till ~715A) | No Beam | No Beam | ILD running possible once HCO complete and BA granted |
Shift Leader | Law | Suleiman | Law | Law | Law | No Beam | No Beam | |
Scientist #2 | No Beam | No Beam | ||||||
Crew Chief | Law | Law | Law | Law | Forman | Forman (?) | Forman (?) | |
SSO | Deir | Deir | Deir | Deir | Deir | Garcia (?) | Garcia (?) | |
DAY Shift | 6/28 | 6/29 | 6/30 | 7/1 | 7/2 | 7/3 | 7/4 🇺🇸 | |
Beam Commissioning Plan (ATLis) |
morning TBD; 12-24 Bunch length system check and measurement | Heat and activate cathode | 8-12 open; 12-16 beam recovery to FC2 | Wien match (500keV Limited until ~2P) |
TBD (500keV Limited until ~2P) |
No Beam | No Beam | |
Shift Leader | morning TBD; 12-24 Kazimi | Grames | Kazimi | Turner | Wang | No Beam | No Beam | |
Scientist #2 | 12-24 Hofler; 12-16 Bruker | Bruker | Hofler | Bruker? | No Beam | No Beam | ||
Crew Chief | Aiken | Aiken | Freeman | Frierson | Merz | Merz (?) | Merz (?) | |
SSO | Gauthier | Gauthier | Gauthier | Jones | Jones | Aiken (?) | Aiken (?) | |
SWING Shift | 6/28 | 6/29 | 6/30 | 7/1 | 7/2 | 7/3 | 7/4 🇺🇸 | |
Beam Commissioning Plan (ATLis) |
12-24 Bunch length system check and measurement | Heat and activate cathode (cont'd), no beam | Bunch length setup Capture FE Characterization |
FC2 Setup | Mott Checkout / FC2 Setup |
No Beam | No Beam | |
Shift Leader | 12-24 Kazimi | Grames | Kazimi | Wang | Suleiman / Wang? | No Beam | No Beam | |
Scientist #2 | 12-24 Hofler | No Beam | No Beam | |||||
Crew Chief | McCaughan | McCaughan | Moser | Moser | Moser | Carlino (?) | Carlino (?) | |
SSO | Mock | Mock | Mock | Mock | Mock | Anthony (?) | Anthony (?) |