Meeting 2/3/22 - COMTRA

From Ciswikidb
Revision as of 15:11, 2 February 2022 by Grames (talk | contribs)
Jump to navigation Jump to search

First installation

  • remove ~4' pipe in straight passthrough
  • add reducer + ceramic break + bubble radiator
  • add MIT bates magnet + Mott detector on the support table
  • realistic time frame for DAQ

Second installation

  • Replace MIT magnet with Lakshmi's magnet
  • Replace Mott detector with Eric's detector

Updates & Discussion

  • Fabricate (2) 6mm Cu radiators
  • Detector specs/status
  • Magnet design/scope