April 21, 2022 - HV chamber layout for installation in CEBAF
Jump to navigation
Jump to search
Agenda
Critical path action items
- Anode flange designed based on Injector Phase 1 but with two HV ports
- Need to order:
- 2 two zero length reducer 10" to 4-1/2" flanges
- 4 weldable 1-1/3" non-rotatable tapped flanges, or already welded to tube. Shaun?
- 4 10 kV SHV feedthroughs. (Marcy, do we have these?, how many?)
- Ceramic beads
- Carlos to look for alternative to Cu wire with lower coefficient of expansion
- Need to order:
Screen Design
Marcy dimension requests media:screens18gun.pptx
Useful documents
- Anode flange prints and pictures
- Media:CIS-ASY-R30-3 schedule updateed April 12 2022.xlsx
- Media:14" HV chamber CEBAF injector vacuum piping dimensions.pptx
Updates
TEAMS meeting link sent along with invite