Wednesday, Mar 15, 2023

Machine shop jobs

UITF jobs

CEBAF jobs

Drury's SRF job in nutshell

3/27 Warm up quarter
4/12 - 4/18 prep the quarter for removal
4/19 - remove quarter from injector
4/20 - install bracing for microphonics mitigation
4/21 - install booster
4/24 - 4/28 prep booster for 4K cool down
5/1 - Cool down booster

Tuesday, Mar 14, 2023

UITF jobs ...

  • Yesterday's run down...
  • Today, what's happening...
  • When does Vince get the plate...?

CEBAF jobs ...

  • Neil would like list of things to crane, should be prepped prior day for:
    • Tue 3/21 (...)
    • Wed 3/22 (...)
  • Viewer/harp ...
    • Which day to vent?
    • Will ask Nate for help, yes?

Monday, Mar 13, 2023

UITF jobs ...

CEBAF jobs next week ...

  • Neil's jobs/when
  • 1st week of SAD
    • S&A first two days
    • Test laser retro, store puck, LTT laser
    • CIS move things to tunnel
    • Vent chopper, repair viewer/harp

Friday, Mar 10, 2023

  • Joe
...found Gun2 has Bulk #32 puck for HV conditioning (i.e. don't need to bring one from UITF) - https://logbooks.jlab.org/entry/3876517
...things to do on Monday ... isolate laser, vacuum valves, disconnect electrical things, stow pucks, HV cable disconnect, move toward clean room
...EH&S approved their part (but needs HV OSP in place if we go that route) => * ATLIS => https://tasklists.jlab.org/atlis/tasks/108541
  • Max
...running final beam test, plans to wrap up today, latest Sunday
...coordinating w/ DC Power and I&C to de-energize and disconnect cables to magnets and bpm's
  • Marcy
...polishing CEBAF install work plan gantt chart, will circulate and review on Monday
...coordinating w/ Vince for modification of "blue" HV chamber base plate next week
  • Steve
...has plan to work with Scott and to document racks/controls during SAD
...let's review laser plan with Shukui (replace Hall A mode-lock with temp regulating seed, continue developing/testing new board for later upgrade)