'''Timeline 2022'''
 +
*April - finish design & assembly of Wien and Mott hardware, finish 200 KV HV vac work
 +
*May - install Wien/Mott UITF, finish 200 KV gun assembly, restore polarized laser UITF
 +
*June - install 200 keV gun, bake, big job, goal is making beam by ~July 4th weekend
 +
*July - make 200 keV polarized beam, calibrate the Mott, using ~nA beam and U-Wien
 +
*Aug - install Compton in MeV section, run keV beam as needed
 +
*Sep/Oct - calibrate Compton, two separate ~week long runs
 +
 +
 +
* [[File:200kV Gun w-CIS-ASY-R30-3 (2) iso.png]]
 +
 
* <span style="font-size:100%"> '''[[Background and status as of July 1 2021]]''' </span>
 
* <span style="font-size:100%"> '''[[Background and status as of July 1 2021]]''' </span>
  
Line 9: Line 20:
 
* <span style="font-size:100%"> '''[[Electrostatic  and beam dynamics simulations]]''' </span>
 
* <span style="font-size:100%"> '''[[Electrostatic  and beam dynamics simulations]]''' </span>
  
; Presentations
+
* <span style="font-size:100%"> '''[[Update meetings]]''' </span>
* 11/15/2021 Simulation of the NEG screen. Shaun's wire Mesh [[Media: 18_in_CEBAF_gun_Mesh_screen.pptx]]
+
 
* 11/02/2021 Simulation of the NEG screen. Missing front view cross-sections [[Media: 18_in_CEBAF_gun_Gabs_screen_FRONT_VIEWS.pptx]]
+
* <span style="font-size:100%"> '''[[Presentations]]''' </span>
* 10/20/2021 Simulation of the NEG screen for 18" CEBAF "a la GTS" gun [[Media: 18_in_CEBAF_gun_Gabs_screen.pptx]]
 
* 10/13/2021 Vacuum chamber passed its pressure test [[Media: HV_pressure_tests_update.pptx]]
 
* 9/22/2021 Gabriel's modeling & simulation for 18" gun [[Media: GTS_gun_with_CEBAF_anode_Shields.pptx]]
 
* 9/15/2021 Marcy options for how NEG's might be mounted [[media:UHV1400MountV2.pptx]]
 

Revision as of 09:40, 31 March 2022

Timeline 2022

  • April - finish design & assembly of Wien and Mott hardware, finish 200 KV HV vac work
  • May - install Wien/Mott UITF, finish 200 KV gun assembly, restore polarized laser UITF
  • June - install 200 keV gun, bake, big job, goal is making beam by ~July 4th weekend
  • July - make 200 keV polarized beam, calibrate the Mott, using ~nA beam and U-Wien
  • Aug - install Compton in MeV section, run keV beam as needed
  • Sep/Oct - calibrate Compton, two separate ~week long runs


  • 200kV Gun w-CIS-ASY-R30-3 (2) iso.png