(Created page with "*NEG ZAO modules have been installed and wired by Marcy Stutzman *Vacuum chamber was cleaned, but NEG coating left untouched *Vacuum chamber was baked with extractor gauge for...")
 
Line 9: Line 9:
 
*[https://logbooks.jlab.org/entry/4037039 gun assembly S&A]
 
*[https://logbooks.jlab.org/entry/4037039 gun assembly S&A]
 
*[https://logbooks.jlab.org/entry/4033360 gun assembled, under vacuum and leak checked]
 
*[https://logbooks.jlab.org/entry/4033360 gun assembled, under vacuum and leak checked]
*
+
*[https://logbooks.jlab.org/entry/4041398 gun under vacuum moved to TL1137]
 +
*The gun fully assembled is being vacuum pre-baked to ~150 C  in TL1137 to ensure there are no leaks, and that the NEG models are not shorted out. Marcy installed a, extractor gauge for vacuum monitoring after bake.
 +
*The plan is to leave the gun under vacuum until ready for installation in UITF beam line, with plans to install in CEBAF tunnel in March 2023.