Line 10: Line 10:
 
*[https://logbooks.jlab.org/entry/4033360 gun assembled, under vacuum and leak checked]
 
*[https://logbooks.jlab.org/entry/4033360 gun assembled, under vacuum and leak checked]
 
*[https://logbooks.jlab.org/entry/4041398 gun under vacuum moved to TL1137]
 
*[https://logbooks.jlab.org/entry/4041398 gun under vacuum moved to TL1137]
*The gun fully assembled is being vacuum pre-baked to ~150 C  in TL1137 to ensure there are no leaks, and that the NEG models are not shorted out. Marcy installed a, extractor gauge for vacuum monitoring after bake.  
+
*The gun fully assembled is being vacuum pre-baked to ~150 C  in TL1137 to ensure there are no leaks, and that the NEG modules are not shorted out. Marcy installed an extractor gauge for vacuum monitoring after bake.  
 
*The plan is to leave the gun under vacuum until ready for installation in UITF beam line, with plans to install in CEBAF tunnel in March 2023.
 
*The plan is to leave the gun under vacuum until ready for installation in UITF beam line, with plans to install in CEBAF tunnel in March 2023.
  
  
 
*[https://wiki.jlab.org/ciswiki/index.php/18%22_Photogun_ala_GTS Back to 18" Photogun page]
 
*[https://wiki.jlab.org/ciswiki/index.php/18%22_Photogun_ala_GTS Back to 18" Photogun page]

Latest revision as of 07:39, 5 October 2022